6512 S 3RD AVE 90043
Certificate Information: 6512 S 3RD AVE 90043
- Application / Permit
- 21014-10000-01328
- Plan Check / Job No.
- B21LA05109
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ONE STORY ADDITION TO (E) GARAGE AND CONVERT TO ADU.
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | JOE VO |
| Corrections Issued | 4/25/2021 | JOE VO |
| Quality Review Completed | 5/4/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/15/2021 | JOE VO |
| Applicant returned to address corrections | 7/13/2021 | JOE VO |
| Applicant returned to address corrections | 11/23/2021 | JOE VO |
| Plan Check Approved | 3/1/2022 | JOE VO |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 8/7/2023 | ENRIQUE MIRELES |
| CofO in Progress | 8/7/2023 | ENRIQUE MIRELES |
| CofO Issued | 8/9/2023 | DEROLD HAUFF |
| Permit Finaled | 8/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2021 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | JEREMY CHOK |
| Hydrant and Access approval | Cleared | 8/13/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/13/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 7/26/2022 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 9/29/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/19/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/17/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/27/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/27/2022 | Corrections Issued | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/30/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/4/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 1/4/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/10/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 3/2/2023 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 3/8/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/14/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/14/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/24/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/3/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 8/3/2023 | Approved | ENRIQUE MIRELES |