4051 W 58TH PL 90043

Certificate Information: 4051 W 58TH PL 90043

Application / Permit
21014-10000-01318
Plan Check / Job No.
B21LA05093
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF (E) DETACHED 1-STORY GARAGE INTO (N) 2-STORY ADU.
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 CRYSTEL MAALOUF
Corrections Issued 4/30/2021 CRYSTEL MAALOUF
Quality Review Completed 5/7/2021 WING SUEN
Applicant returned to address corrections 7/29/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 8/5/2021 CRYSTEL MAALOUF
Building Plans Picked Up 8/6/2021 APPLICANT
Plan Check Approved 10/18/2021 CRYSTEL MAALOUF
Issued 11/9/2021 APPLICANT
CofO in Progress 6/12/2023 ENRIQUE MIRELES
CofO in Progress 6/12/2023 ENRIQUE MIRELES
No Progress 10/18/2023 SCOTT FINNILA
CofO in Progress 12/15/2023 SCOTT FINNILA
No Progress 4/23/2024 SCOTT FINNILA
CofO in Progress 4/23/2024 SCOTT FINNILA
CofO Issued 5/1/2024 DEROLD HAUFF
Permit Finaled 5/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/1/2021 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 6/3/2021 JEREMY CHOK
Sewer availability Cleared 6/3/2021 JEREMY CHOK
Roof/Waste drainage to street Cleared 7/29/2021 JEREMY CHOK
Grading Pre-Inspection Cleared 8/24/2021 BARTON HOLMES
Hydrant and Access approval Cleared 9/12/2021 RUEL COLE
Construction near power lines Cleared 9/20/2021 WALTER RAMIREZ
GPI Written Notices Cleared 10/18/2021 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/31/2022 Approved ENRIQUE MIRELES
Underground Mechanical 6/8/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/10/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/17/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Partial Approval RYAN SALAZAR
Sewer 9/14/2022 Approved RYAN SALAZAR
Wood Frame 9/14/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/4/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Approved ENRIQUE MIRELES
HVAC-Rough 10/4/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/9/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 11/9/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/9/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/16/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/30/2022 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 11/30/2022 Approved JAMES CHAVEZ
Insulation 12/8/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 12/16/2022 Partial Approval ENRIQUE MIRELES
Insulation 12/16/2022 Partial Approval ENRIQUE MIRELES
Interior/Exterior Lathing 12/16/2022 Approved ENRIQUE MIRELES
Drywall Nailing 1/12/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/28/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/21/2023 Approved ENRIQUE MIRELES
Shower Pan 3/21/2023 Approved ENRIQUE MIRELES
Final 5/18/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/18/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/18/2023 Approved ENRIQUE MIRELES
Final 5/30/2023 Corrections Issued ENRIQUE MIRELES
Final 6/9/2023 OK to Issue CofO ENRIQUE MIRELES