6043 E BUENA VISTA TER 90042
Certificate Information: 6043 E BUENA VISTA TER 90042
- Application / Permit
- 21014-10000-01316
- Plan Check / Job No.
- B21LA05085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d) AND 2ND STORY ADDITION W/ROOFTOP DECK
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | LAMAR DAVIS |
| Corrections Issued | 5/3/2021 | LAMAR DAVIS |
| Quality Review Completed | 5/12/2021 | WING SUEN |
| Plan Check Approved | 1/25/2022 | LAMAR DAVIS |
| Issued | 3/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| CofO in Progress | 11/25/2025 | RONNIE MEDINA |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
| CofO Issued | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 5/27/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 5/27/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 5/27/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 5/27/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 5/27/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/7/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 9/4/2021 | RUEL COLE |
| GPI Written Notices | Cleared | 10/27/2021 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 10/27/2021 | ROBERT HUGHES |
| Low Impact Development | Cleared | 12/14/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/5/2022 | JEANETTE VONG |
Contact Information
| Architect | Smith,, Carl Francis; Lic. No.: C29671 | 672 S AVENUE 21 # 2 LOS ANGELES, CA 90031 |
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Geologist | Nguyen,, An Wong; Lic. No.: EG2468 | 5913 SATURN STREET LOS ANGELES, CA 90035 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 5/22/2023 | Corrections Issued | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 5/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 5/24/2023 | Partial Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/30/2023 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Partial Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 9/5/2023 | Partial Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 9/14/2023 | Approved | ROY SPAULDING |
| Masonry Wall/Backfill | 9/26/2023 | Approved | ROY SPAULDING |
| Deputy Reinf. Concrete | 10/4/2023 | Conditional Approval | ROY SPAULDING |
| Masonry Wall/Backfill | 10/13/2023 | Partial Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 11/28/2023 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Partial Approval | CRAIG VAUGHAN |
| Light Gage Steel Frame | 2/14/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/12/2024 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 3/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/29/2024 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/7/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Conditional Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 10/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/30/2024 | Partial Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 10/30/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 11/26/2024 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 12/3/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 12/3/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 12/3/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/3/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/5/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 1/14/2025 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 2/20/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/20/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Special/Order Compliance | 2/20/2025 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 2/27/2025 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 3/6/2025 | Approved | JOSH MEISTER |
| Special/Order Compliance | 3/12/2025 | Corrections Issued | JOSH MEISTER |
| Interior/Exterior Lathing | 5/15/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 9/11/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 10/3/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 10/6/2025 | Approved | DAVID WILLIAMS |
| Final | 10/27/2025 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 10/27/2025 | Corrections Issued | RONNIE MEDINA |
| Reinforced Masonry Frame | 10/27/2025 | Partial Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 10/27/2025 | Approved | RONNIE MEDINA |
| Structural Steel Frame | 10/27/2025 | Partial Inspection | RONNIE MEDINA |
| Final | 11/25/2025 | OK to Issue CofO | RONNIE MEDINA |
| Green Building Final | 11/25/2025 | Approved | RONNIE MEDINA |
| Reinforced Masonry Frame | 11/25/2025 | Approved | RONNIE MEDINA |
| Structural Steel Frame | 11/25/2025 | Approved | RONNIE MEDINA |