206 W 118TH ST 90061

Certificate Information: 206 W 118TH ST 90061

Application / Permit
21014-10000-01285
Plan Check / Job No.
B21LA04939
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2 CAR GARAGE INTO ACCESSORY DWELLING UNIT WITH ADDITION (12'-5" X 28'-0") Per Ordinance
Permit Issued
Issued on 6/17/2021
Issuing Office
Metro
Current Status
CofO Issued on 7/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/19/2021 FARSHAD ALIMOHAMADI
Corrections Issued 3/20/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 5/14/2021 LUKE GONZALES
Issued 6/17/2021 APPLICANT
Building Plans Picked Up 6/21/2021 APPLICANT
CofO in Progress 6/8/2022 JOHN KLARIN
Permit Finaled 7/6/2022 DEROLD HAUFF
CofO Issued 7/6/2022 DEROLD HAUFF
Permit Finaled 7/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/12/2021 ELENA LOPEZ
Construction near power lines Cleared 4/12/2021 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 4/12/2021 ELENA LOPEZ
Roof/Waste drainage to street Cleared 4/12/2021 ELENA LOPEZ
Sewer availability Cleared 4/12/2021 ELENA LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 8/23/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 8/26/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/3/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/8/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/18/2021 Partial Approval CRAIG DAVIS
Green Building Rough 10/18/2021 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 10/18/2021 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 11/15/2021 Approved JOHN KLARIN
Gas Test 12/20/2021 Approved JOHN KLARIN
Underground Mechanical 12/20/2021 Approved JOHN KLARIN
PLUMBING-Final 12/23/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 1/4/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/4/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 1/7/2022 Approved EUGENE CASSIDY
Green Building Rough 1/7/2022 Approved EUGENE CASSIDY
HVAC-Rough 1/7/2022 Approved EUGENE CASSIDY
MERV13>=Rough 1/7/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 1/7/2022 Approved EUGENE CASSIDY
Insulation 1/13/2022 Approved EUGENE CASSIDY
Drywall Nailing 1/24/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/27/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 1/27/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/14/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 4/4/2022 Approved ALIZAH MAYAGOITIA
Final 5/11/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 5/11/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 5/11/2022 Approved ALIZAH MAYAGOITIA
Final 6/7/2022 OK to Issue CofO JOHN KLARIN
Green Building Final 6/7/2022 Approved JOHN KLARIN
HVAC-Final 6/7/2022 Approved JOHN KLARIN
PLUMBING-Final 6/7/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved JOHN KLARIN