747 W 104TH PL 90044

Certificate Information: 747 W 104TH PL 90044

Application / Permit
21014-10000-01283
Plan Check / Job No.
B21LA04930
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY ADDITION AT REAR OF SINGLE FAMILY DWELLING TO ADD 1 BEDROOM AND 1 BATHROOM
Permit Issued
Issued on 6/16/2021
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SINA KHOSRAVI
Corrections Issued 3/23/2021 SINA KHOSRAVI
Plan Check Approved 5/4/2021 TSE MING HUANG
Building Plans Picked Up 5/11/2021 APPLICANT
Issued 6/16/2021 APPLICANT
CofO in Progress 3/7/2024 JAMES CHAVEZ
CofO Issued 3/7/2024 ANSON MAGLASANG
Permit Finaled 3/7/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/9/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 4/9/2021 THOMAS LANG
Sewer availability Cleared 4/9/2021 THOMAS LANG

Contact Information

Contractor Solis Carlos; Lic. No.: 732102-B 1147 E 91ST ST      LOS ANGELES, CA 90002

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/20/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/23/2021 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 8/16/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/1/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 9/1/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/1/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval EUGENE CASSIDY
Insulation 9/3/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/24/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/24/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved EUGENE CASSIDY
Green Building Rough 9/24/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 9/24/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 9/24/2021 Approved EUGENE CASSIDY
Insulation 9/30/2021 Approved EUGENE CASSIDY
Drywall Nailing 10/5/2021 Approved EUGENE CASSIDY
Green Building Rough 10/5/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/8/2022 Approved JOHN KLARIN
ELECTRICAL-Final 2/8/2022 Not Ready for Inspection JOHN KLARIN
Final 2/8/2022 Corrections Issued JOHN KLARIN
Green Building Final 2/8/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 2/8/2022 Corrections Issued JOHN KLARIN
Final 2/17/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 2/17/2022 Approved ANSON MAGLASANG
Service/Power Release 2/17/2022 Approved ANSON MAGLASANG
Smoke Detectors 2/17/2022 Approved ANSON MAGLASANG
Final 11/7/2022 Not Ready for Inspection JOHN KLARIN
Final 12/19/2022 Partial Inspection JAMES CHAVEZ
Final 3/6/2024 OK to Issue CofO JAMES CHAVEZ