376 N RIDGEWOOD PL 90004
Certificate Information: 376 N RIDGEWOOD PL 90004
- Application / Permit
- 21014-10000-01282
- Plan Check / Job No.
- B21LA04929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 1-CAR DETACHED GARGAGE (226 SF ZONING) TO ADU AND ADDITION PER ENGINEER DESIGN (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 9/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | AUNG SOE |
| Corrections Issued | 3/22/2021 | AUNG SOE |
| Applicant returned to address corrections | 8/24/2021 | AUNG SOE |
| Plan Check Approved | 8/25/2021 | AUNG SOE |
| Issued | 9/2/2021 | APPLICANT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| CofO in Progress | 4/5/2022 | SHAVONNE ESPINOZA |
| Permit Finaled | 2/22/2023 | DEROLD HAUFF |
| CofO Issued | 2/22/2023 | DEROLD HAUFF |
| Permit Finaled | 2/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/21/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/21/2021 | RIDWAN HARDY |
| Address approval | Cleared | 7/28/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | THOMAS LANG |
| Sewer availability | Cleared | 8/12/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/8/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 9/17/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 9/24/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/24/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 9/24/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 10/25/2021 | Conditional Approval | MASHEL JONGERT |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/12/2021 | Approved | MASHEL JONGERT |
| HVAC-Rough | 11/12/2021 | Approved | MASHEL JONGERT |
| PLUMBING-Rough | 11/12/2021 | Approved | MASHEL JONGERT |
| Underground Mechanical | 11/12/2021 | Approved | MASHEL JONGERT |
| Wood Frame | 11/12/2021 | Approved | MASHEL JONGERT |
| Insulation | 11/19/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/29/2021 | Approved | MASHEL JONGERT |
| Shower Pan | 11/29/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 12/8/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/3/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 3/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 3/7/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 3/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Final | 3/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| HVAC-Final | 3/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Final | 3/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Pre-Inspection | 3/15/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 3/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 3/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 3/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 3/22/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 4/4/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 4/4/2022 | OK to Issue CofO | SHAVONNE ESPINOZA |
| HVAC-Final | 4/4/2022 | Approved | SHAVONNE ESPINOZA |