376 N RIDGEWOOD PL 90004

Certificate Information: 376 N RIDGEWOOD PL 90004

Application / Permit
21014-10000-01282
Plan Check / Job No.
B21LA04929
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1-CAR DETACHED GARGAGE (226 SF ZONING) TO ADU AND ADDITION PER ENGINEER DESIGN (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
CofO Issued on 2/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 AUNG SOE
Corrections Issued 3/22/2021 AUNG SOE
Applicant returned to address corrections 8/24/2021 AUNG SOE
Plan Check Approved 8/25/2021 AUNG SOE
Issued 9/2/2021 APPLICANT
Building Plans Picked Up 9/3/2021 APPLICANT
CofO in Progress 4/5/2022 SHAVONNE ESPINOZA
Permit Finaled 2/22/2023 DEROLD HAUFF
CofO Issued 2/22/2023 DEROLD HAUFF
Permit Finaled 2/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 7/21/2021 RIDWAN HARDY
Construction within easement Cleared 7/21/2021 RIDWAN HARDY
Address approval Cleared 7/28/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/2/2021 THOMAS LANG
Sewer availability Cleared 8/12/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 8/17/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2021 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/17/2021 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 9/21/2021 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/24/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/24/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 9/24/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 10/25/2021 Conditional Approval MASHEL JONGERT
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 10/26/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/12/2021 Approved MASHEL JONGERT
HVAC-Rough 11/12/2021 Approved MASHEL JONGERT
PLUMBING-Rough 11/12/2021 Approved MASHEL JONGERT
Underground Mechanical 11/12/2021 Approved MASHEL JONGERT
Wood Frame 11/12/2021 Approved MASHEL JONGERT
Insulation 11/19/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/19/2021 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 11/29/2021 Approved MASHEL JONGERT
Shower Pan 11/29/2021 Approved MASHEL JONGERT
Interior/Exterior Lathing 12/8/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/3/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/3/2022 Approved ARTHUR SARGSYAN
Final 3/3/2022 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/3/2022 Approved ARTHUR SARGSYAN
Green Building Rough 3/3/2022 Approved ARTHUR SARGSYAN
HVAC-Final 3/3/2022 Approved ARTHUR SARGSYAN
PLUMBING-Final 3/3/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/3/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/7/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Final 3/7/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Final 3/7/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 3/10/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Final 3/10/2022 Not Ready for Inspection SHAVONNE ESPINOZA
HVAC-Final 3/10/2022 Not Ready for Inspection SHAVONNE ESPINOZA
PLUMBING-Final 3/10/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Pre-Inspection 3/15/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Final 3/22/2022 Corrections Issued SHAVONNE ESPINOZA
Final 3/22/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Final 3/22/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Final 3/22/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 4/4/2022 Approved SHAVONNE ESPINOZA
Final 4/4/2022 OK to Issue CofO SHAVONNE ESPINOZA
HVAC-Final 4/4/2022 Approved SHAVONNE ESPINOZA