1813 W 80TH ST 90047

Certificate Information: 1813 W 80TH ST 90047

Application / Permit
21014-10000-01250
Plan Check / Job No.
B21LA04857
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan: CONVERT EXISTING GARAGE TO ADU AND ADDITION PER LAMC 12.22 A.33(c) AND (d) AND PER WFPP
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 CRYSTEL MAALOUF
Corrections Issued 4/25/2021 CRYSTEL MAALOUF
Quality Review Completed 5/4/2021 HERNAN ARREOLA
Applicant returned to address corrections 11/18/2021 CRYSTEL MAALOUF
Plan Check Approved 12/9/2021 CRYSTEL MAALOUF
Issued 12/15/2021 APPLICANT
CofO in Progress 3/14/2023 ENRIQUE MIRELES
CofO in Progress 3/14/2023 ENRIQUE MIRELES
Permit Finaled 5/16/2023 DEROLD HAUFF
CofO Issued 5/16/2023 DEROLD HAUFF
Permit Finaled 5/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/30/2021 JEANIE LAM
Sewer availability Cleared 8/31/2021 JEANIE LAM
Hydrant and Access approval Cleared 11/5/2021 KURT CORRAL
Construction near power lines Cleared 11/22/2021 RIDWAN HARDY
Construction within easement Cleared 11/22/2021 RIDWAN HARDY

Contact Information

Contractor Funes Construction Inc; Lic. No.: 1028108-B 14154 ERWIN ST APT 6      VAN NUYS, CA 91401

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/18/2022 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 3/23/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/7/2022 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/12/2022 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/15/2022 Corrections Issued HORACE FULTZ
Excavation/Setback/Form/Re-Bar 4/19/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/27/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/27/2022 Approved ENRIQUE MIRELES
Green Building Rough 5/27/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/27/2022 Approved ENRIQUE MIRELES
Insulation 6/14/2022 Approved ENRIQUE MIRELES
Drywall Nailing 7/6/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/7/2022 Approved ENRIQUE MIRELES
Final 12/7/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 12/7/2022 Approved ENRIQUE MIRELES
Green Building Final 12/7/2022 Approved ENRIQUE MIRELES
HVAC-Final 12/7/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 12/7/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/7/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/12/2022 Approved ENRIQUE MIRELES
Final 12/12/2022 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 12/12/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 12/12/2022 Approved ENRIQUE MIRELES