2100 N SAN YSIDRO DR 90210

Certificate Information: 2100 N SAN YSIDRO DR 90210

Application / Permit
21014-10000-01243
Plan Check / Job No.
B21LA04846
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 DANIEL YIP
Corrections Issued 3/22/2021 DANIEL YIP
Quality Review Completed 3/27/2021 HERNAN ARREOLA
Plan Check Approved 9/8/2021 DANIEL YIP
Issued 9/27/2021 APPLICANT
CofO in Progress 5/11/2023 MICHAEL PELHAM
Permit Finaled 5/11/2023 DANIEL ORRANTE
CofO Issued 5/11/2023 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/26/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/26/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/26/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/26/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/26/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 4/27/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 6/11/2021 KURT CORRAL
Sewer availability Cleared 6/13/2021 DENNIS BRAGIN
ZI Cleared 7/23/2021 DENZEL HENDERSON
Roof/Waste drainage to street Cleared 8/9/2021 DINAH GARIN
GPI Written Notices Cleared 9/8/2021 DANIEL YIP
Grading Pre-Inspection Cleared 9/8/2021 DANIEL YIP
Low Impact Development Cleared 9/8/2021 JORGE MEJIA LEMUS
Hold Cleared 11/4/2021 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504
Engineer Zhang,, Quguang; Lic. No.: L8968 9080 TELSTAR AVE 303      EL MONTE, CA 91731

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/26/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 2/10/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/10/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 6/8/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 6/8/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/8/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/16/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/16/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 6/16/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/5/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/5/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/5/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/5/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/13/2022 Corrections Issued STEPHANIE SWANSON
Insulation 7/19/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 7/27/2022 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/27/2022 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/27/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/27/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 7/27/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/28/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 8/18/2022 Approved EVAN COOPER
Shower Pan 8/18/2022 Approved EVAN COOPER
Gas Test 1/20/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 1/20/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 3/8/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Gas Test 3/8/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 3/8/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 4/6/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 4/6/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 5/11/2023 OK to Issue CofO MICHAEL PELHAM