727 1/4 W 73RD ST 90044
Certificate Information: 727 1/4 W 73RD ST 90044
- Application / Permit
- 21014-10000-01237
- Plan Check / Job No.
- B21LA04827
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground floor addition to an (E) detached garage and conversion of a portion of an (E) detached garage and new addition into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 7/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2021 | HELEN NGUYEN |
| Corrections Issued | 3/22/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/21/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/15/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/16/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/28/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 8/2/2021 | HELEN NGUYEN |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 7/6/2023 | MICHAEL LEWIS |
| Permit Finaled | 7/28/2023 | DEROLD HAUFF |
| CofO Issued | 7/28/2023 | DEROLD HAUFF |
| Permit Finaled | 7/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | CELINA MORENO |
| Sewer availability | Cleared | 6/14/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2021 | THOMAS LANG |
Contact Information
| Architect | Cataldo,, John G; Lic. No.: C10457 | 835 MISSION STREET SOUTH PASADENA, CA 91030 |
| Contractor | I S M C; Lic. No.: 866197-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 9/15/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 9/15/2021 | Corrections Issued | LEOPOLDO MENDOZA |
| Wood Frame | 9/15/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Underground Mechanical | 9/26/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/4/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 1/4/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 1/5/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/10/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 1/10/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 1/17/2023 | Approved | LILIANA PORTILLO |
| Wood Frame | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/26/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 2/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/1/2023 | Approved | LILIANA PORTILLO |
| Insulation | 2/6/2023 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/6/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 2/13/2023 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 3/6/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 5/2/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/12/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 5/12/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 5/16/2023 | Approved | MICHAEL LEWIS |
| Final | 5/16/2023 | Partial Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/16/2023 | Conditional Approval | MICHAEL LEWIS |
| HVAC-Final | 5/16/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 5/16/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 5/18/2023 | Approved | MICHAEL LEWIS |
| Final | 6/26/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/26/2023 | Approved | MICHAEL LEWIS |
| Final | 7/6/2023 | OK to Issue CofO | MICHAEL LEWIS |