226 1/2 E 103RD ST 90003

Certificate Information: 226 1/2 E 103RD ST 90003

Application / Permit
21014-10000-01230
Plan Check / Job No.
B21LA04760
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE AND CARPORT WITH NEW ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 KEVIN MORALES
Corrections Issued 3/18/2021 KEVIN MORALES
Applicant returned to address corrections 3/29/2021 KEVIN MORALES
Plan Check Approved 4/7/2021 CRYSTEL MAALOUF
Issued 4/16/2021 APPLICANT
CofO in Progress 6/21/2025 DAVID FEILER
Permit Finaled 6/25/2025 RICHARD STEINBACH
CofO Issued 6/25/2025 RICHARD STEINBACH
Permit Finaled 6/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/19/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 3/19/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/31/2021 CECILIO NAVARRO
Sewer availability Cleared 3/31/2021 CECILIO NAVARRO

Contact Information

Contractor All In One Construction; Lic. No.: 674782-B 1056 CYPRESS AVENUE #H      LA HABRA, CA 90631
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2021 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 6/2/2021 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 6/2/2021 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 6/2/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/2/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/6/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/13/2021 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 7/16/2021 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 7/20/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 8/20/2021 Partial Approval EUGENE CASSIDY
Sewer 8/24/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 9/24/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/24/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 9/28/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 10/1/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Approved EUGENE CASSIDY
Green Building Rough 10/1/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 10/1/2021 Approved EUGENE CASSIDY
Insulation 12/1/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 12/6/2021 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 12/6/2021 Conditional Approval WILLIAM ROSE
Insulation 12/6/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 12/20/2021 Not Ready for Inspection ANSON MAGLASANG
Insulation 12/20/2021 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 12/27/2021 Approved ANSON MAGLASANG
Insulation 12/27/2021 Approved ANSON MAGLASANG
Drywall Nailing 1/4/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 2/4/2022 Approved AMY COLIN
Shower Pan 2/10/2022 Approved JOHN KLARIN
Service/Power Release 5/3/2022 No Access for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready JOHN KLARIN
Final 8/2/2022 Corrections Issued JOHN KLARIN
Green Building Final 8/2/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/2/2022 Corrections Issued JOHN KLARIN
Final 10/11/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 10/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 10/11/2022 Approved ALIZAH MAYAGOITIA
Final 12/27/2022 Corrections Issued JOHN KLARIN
Green Building Final 12/27/2022 Approved JOHN KLARIN
Final 2/8/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 3/7/2023 Approved JOHN KLARIN
Final 3/7/2023 Not Ready for Inspection JOHN KLARIN
HVAC-Final 3/7/2023 Approved JOHN KLARIN
PLUMBING-Final 3/7/2023 Approved JOHN KLARIN
Final 6/21/2025 OK to Issue CofO DAVID FEILER