12699 W KLING ST 91604
Certificate Information: 12699 W KLING ST 91604
- Application / Permit
- 21014-10000-01229
- Plan Check / Job No.
- B21LA04748
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU AND ADD [10 X 20] PATIO COVER PER IB. WORK PER WFPP
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2021 | JESSE JIMENEZ |
| Corrections Issued | 3/24/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/23/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 5/17/2021 | ADAM HEGAZI |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 8/16/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/23/2022 | RONALD MYRICK |
| CofO Issued | 8/23/2022 | RONALD MYRICK |
| Permit Finaled | 8/23/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/12/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/16/2021 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/18/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/23/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 12/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 12/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 12/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/15/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/17/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 2/17/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/17/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/17/2022 | Partial Approval | ARAM AVEDISIAN |
| MERV13>=Rough | 2/17/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 2/23/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/2/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 8/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 8/2/2022 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 8/2/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 8/2/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/2/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 8/3/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/3/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 8/3/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 8/3/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 8/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/10/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 8/10/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 8/10/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 8/10/2022 | Approved | CHRISTOPHE COCHRAN |