4952 E MERIDIAN ST 90042
Certificate Information: 4952 E MERIDIAN ST 90042
- Application / Permit
- 21014-10000-01211
- Plan Check / Job No.
- B21LA04642
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TWO STORY ADDITION TO EXISTING DETACHED GARAGE FOR NEW REC. ROOM WITH ADU ON 2ND FLOOR. (GARAGE TO REMAIN)
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- CofO Issued on 9/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | JOE VO |
| Corrections Issued | 4/14/2021 | JOE VO |
| Quality Review Completed | 4/22/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 5/15/2021 | JOE VO |
| Plan Check Approved | 7/23/2021 | JOE VO |
| Issued | 7/29/2021 | APPLICANT |
| CofO in Progress | 8/1/2022 | CRAIG VAUGHAN |
| CofO in Progress | 8/1/2022 | CRAIG VAUGHAN |
| Permit Finaled | 9/6/2022 | DEROLD HAUFF |
| CofO Issued | 9/6/2022 | DEROLD HAUFF |
| Permit Finaled | 9/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/27/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 6/2/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 6/9/2021 | OSCAR CASTRO |
| Low Impact Development | Cleared | 7/14/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/15/2021 | JEANIE LAM |
Contact Information
| Contractor | Al Ramirez Construction Inc; Lic. No.: 749564-B | 4950 MERIDIAN ST LOS ANGELES, CA 90042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/2/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/12/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/26/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 8/26/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 9/30/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/30/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 9/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 10/14/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/14/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/20/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/20/2021 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 11/9/2021 | Corrections Issued | CRAIG VAUGHAN |
| Deck | 11/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/15/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 11/15/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 11/17/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 11/29/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 11/29/2021 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 11/29/2021 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 12/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 12/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 12/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/6/2022 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/24/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/18/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 4/18/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/18/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/7/2022 | Approved | SCOTT FINNILA |
| Final | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 7/7/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 7/7/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 7/7/2022 | Conditional Approval | SCOTT FINNILA |
| Smoke Detectors | 7/7/2022 | Approved | SCOTT FINNILA |
| Final | 7/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 7/29/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 7/29/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 7/29/2022 | Approved | CRAIG VAUGHAN |