404 E 93RD ST 90003

Certificate Information: 404 E 93RD ST 90003

Application / Permit
21014-10000-01185
Plan Check / Job No.
B21LA04558
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Convert Existing Detached rec room/storage into an ADU per ordinance, scope will also consist of a addition in the rear.
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 8/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 MICHAEL LOPEZ
Corrections Issued 4/19/2021 MICHAEL LOPEZ
Quality Review Completed 4/26/2021 WING SUEN
Applicant returned to address corrections 3/16/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/17/2022 MICHAEL LOPEZ
Applicant returned to address corrections 5/11/2022 MICHAEL LOPEZ
Applicant returned to address corrections 5/27/2022 MICHAEL LOPEZ
Plan Check Approved 6/10/2022 MICHAEL LOPEZ
Issued 6/10/2022 APPLICANT
CofO in Progress 8/1/2023 JAMES CHAVEZ
Permit Finaled 8/3/2023 ANSON MAGLASANG
CofO Issued 8/3/2023 ANSON MAGLASANG
Permit Finaled 8/3/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/2/2021 WALLIE JONG
ZA Case Cleared 11/10/2021 MAXFIELD VERMY
ZA Case Cleared 11/10/2021 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 2/4/2022 CHRISTOPHER ROCHA
Address approval Cleared 2/11/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 3/25/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/4/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 8/4/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/12/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 9/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 9/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 9/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/16/2022 Not Ready for Inspection JOHN KLARIN
Rough-Elec/Plmb/HVAC 9/16/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 9/21/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 9/21/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/21/2022 Approved ALIZAH MAYAGOITIA
Wood Frame 9/21/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/18/2022 Partial Approval ALIZAH MAYAGOITIA
Insulation 10/18/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/18/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 10/24/2022 Approved JOHN KLARIN
Drywall Nailing 11/3/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/16/2023 Approved JOHN KLARIN
ELECTRICAL-Final 5/16/2023 Corrections Issued JOHN KLARIN
Final 5/16/2023 Corrections Issued JOHN KLARIN
Gas Test 5/16/2023 Approved JOHN KLARIN
Green Building Final 5/16/2023 Approved JOHN KLARIN
Green Building Rough 5/16/2023 Approved JOHN KLARIN
HVAC-Final 5/16/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 5/16/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 5/16/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 5/16/2023 Approved JOHN KLARIN
ELECTRICAL-Final 7/18/2023 Approved JAMES CHAVEZ
Final 7/18/2023 OK to Issue CofO JAMES CHAVEZ
HVAC-Final 7/18/2023 Approved JAMES CHAVEZ
PLUMBING-Final 7/18/2023 Approved JAMES CHAVEZ
Service/Power Release 7/18/2023 Approved JAMES CHAVEZ