14821 W OTSEGO ST 91403

Certificate Information: 14821 W OTSEGO ST 91403

Application / Permit
21014-10000-01182
Plan Check / Job No.
B21LA04550
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert existing 280 sf garage to ADU and add 163 additional sf.
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 ARSALAN SHABESTARI
Corrections Issued 4/13/2021 ARSALAN SHABESTARI
Quality Review Completed 4/22/2021 MICHAEL PEREZ
Applicant returned to address corrections 5/21/2021 ARSALAN SHABESTARI
Plan Check Approved 5/25/2021 ARSALAN SHABESTARI
Issued 6/9/2021 APPLICANT
CofO in Progress 2/17/2022 JACK KARGODORIAN
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/22/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/22/2021 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 4/22/2021 GUILLERMO PETRA
Sewer availability Cleared 4/22/2021 GUILLERMO PETRA
ZI Cleared 4/28/2021 ANACANY HURTADO

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B 20501 VENTURA BLVD #135      WOODLAND HILLS, CA 91364

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2021 Partial Approval CHARLES POWELL
Sewer 7/15/2021 Approved CHARLES POWELL
Underground Mechanical 7/15/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 7/21/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 8/25/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 8/25/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 8/25/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 8/25/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 9/22/2021 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/22/2021 Approved ALIZAH MAYAGOITIA
HVAC-Rough 9/22/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/22/2021 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval MISAEL ESPARZA
HVAC-Rough 9/23/2021 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 9/23/2021 Approved MISAEL ESPARZA
Wood Frame 9/23/2021 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 9/24/2021 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/30/2021 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Approved ALIZAH MAYAGOITIA
HVAC-Rough 9/30/2021 Approved ALIZAH MAYAGOITIA
Insulation 10/5/2021 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 10/5/2021 Approved ASHLEY THOMPSON
Shower Pan 10/5/2021 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 10/22/2021 Partial Approval JACK KARGODORIAN
Shower Pan 10/22/2021 Approved JACK KARGODORIAN
Insulation 11/1/2021 Approved MICHAEL PELHAM
Drywall Nailing 11/9/2021 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 11/16/2021 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 11/22/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/31/2022 Approved JACK KARGODORIAN
Final 1/31/2022 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 1/31/2022 Approved JACK KARGODORIAN
Final 2/9/2022 Not Ready for Inspection JACK KARGODORIAN
Final 2/17/2022 OK to Issue CofO JACK KARGODORIAN