9401 N NOBLE AVE 91343

Certificate Information: 9401 N NOBLE AVE 91343

Application / Permit
21014-10000-01180
Plan Check / Job No.
B21LA04531
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached storage building into ADU. New 1 story addition to the ADU to consist of three bedrooms, and two bathrooms.
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 JOE VO
Corrections Issued 3/23/2021 JOE VO
Quality Review Completed 3/30/2021 MICHAEL PEREZ
Plan Check Approved 6/2/2021 JOE VO
Issued 6/8/2021 APPLICANT
CofO in Progress 11/1/2021 CHRISTOPHER DELLEFIELD
Permit Finaled 12/3/2021 MICHAEL SMITH
CofO Issued 12/3/2021 MICHAEL SMITH
Permit Finaled 12/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/1/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/1/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/1/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/1/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 5/20/2021 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/17/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 6/17/2021 Approved GREGG CUMMINGS
ELECTRICAL-Rough 7/29/2021 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval GREGG CUMMINGS
HVAC-Rough 7/29/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 7/29/2021 Approved GREGG CUMMINGS
Underground Mechanical 7/29/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/3/2021 Approved GREGG CUMMINGS
ELECTRICAL-Rough 8/3/2021 Approved GREGG CUMMINGS
Sewer 8/3/2021 Approved GREGG CUMMINGS
Underground Mechanical 8/3/2021 Approved GREGG CUMMINGS
Insulation 8/9/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/9/2021 Partial Approval JAVIER RAMOS JR
Shower Pan 8/9/2021 Approved JAVIER RAMOS JR
Drywall Nailing 8/13/2021 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/13/2021 Partial Approval GREGG CUMMINGS
Final 10/4/2021 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 10/4/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 11/1/2021 Approved CHRISTOPHER DELLEFIELD
Final 11/1/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 11/1/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/1/2021 Approved CHRISTOPHER DELLEFIELD