1320 1/2 S GENESEE AVE 90019

Certificate Information: 1320 1/2 S GENESEE AVE 90019

Application / Permit
21014-10000-01175
Plan Check / Job No.
B21LA04499
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing detached Garage into an ADU w/ loft .
Permit Issued
Issued on 12/12/2022
Issuing Office
Current Status
CofO Issued on 2/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/19/2021 CARLOS MONTES
Corrections Issued 3/19/2021 CARLOS MONTES
Plan Check Approved 11/17/2022 HERNAN ARREOLA
Issued 12/12/2022 APPLICANT
CofO in Progress 1/29/2025 RAUL BARAJAS
Permit Finaled 2/2/2025 DEROLD HAUFF
CofO Issued 2/2/2025 DEROLD HAUFF
Permit Finaled 2/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/23/2022 KHOUNG LE
Roof/Waste drainage to street Cleared 3/23/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 5/17/2022 KHOUNG LE
Sewer availability Cleared 5/17/2022 KHOUNG LE

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/10/2023 Approved JOSE AVILA
Pre-Inspection 3/13/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 5/10/2023 Corrections Issued JOSE AVILA
METHANE-Barrier 5/10/2023 Corrections Issued JOSE AVILA
METHANE-Subgrade 5/10/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/10/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 5/18/2023 Approved JOSE AVILA
METHANE-Barrier 5/18/2023 Approved JOSE AVILA
METHANE-Subgrade 5/18/2023 Approved JOSE AVILA
PLUMBING-Rough 5/18/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 6/7/2023 Partial Approval STUART CHAPMAN
Green Building Rough 6/7/2023 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 6/7/2023 Approved STUART CHAPMAN
PLUMBING-Rough 6/7/2023 Approved STUART CHAPMAN
Sewer 8/11/2023 Approved JOSE AVILA
Underground Mechanical 9/6/2023 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/12/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/17/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/21/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 1/12/2024 Corrections Issued RONNIE MINDANAO
Green Building Rough 1/12/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 1/12/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 1/29/2024 Approved BRENDAN MORELLI
Pre-Inspection 2/6/2024 Partial Inspection STUART CHAPMAN
Insulation 2/15/2024 Approved STUART CHAPMAN
Drywall Nailing 3/8/2024 Approved JOSH MEISTER
Green Building Rough 3/8/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 4/2/2024 Partial Approval RICHARD DOCKUS
ELECTRICAL-Final 8/9/2024 Corrections Issued ARTHUR NEGRETE
Special/Order Compliance 8/9/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Final 9/12/2024 No Access for Inspection ANTHONY RAMOS
PLUMBING-Final 9/13/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 10/10/2024 Approved ARTHUR NEGRETE
Final 10/10/2024 Partial Inspection ARTHUR NEGRETE
Green Building Final 10/10/2024 Partial Approval ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 10/10/2024 Approved ARTHUR NEGRETE
Smoke Detectors 10/10/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 12/6/2024 Approved ARTHUR NEGRETE
Final 1/29/2025 OK to Issue CofO RAUL BARAJAS
Green Building Final 1/29/2025 Approved RAUL BARAJAS