6235 N CARTWRIGHT AVE 91606

Certificate Information: 6235 N CARTWRIGHT AVE 91606

Application / Permit
21014-10000-01165
Plan Check / Job No.
B21LA04477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage and add 2nd floor to create a two story accessory dwelling unit per Ordinance LAMC 12.22A.33(b)(6)
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
CofO Issued on 10/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/14/2021 VU NGUYEN
Corrections Issued 3/14/2021 VU NGUYEN
Plan Check Approved 8/27/2021 VU NGUYEN
Issued 9/10/2021 APPLICANT
CofO in Progress 10/3/2022 JOHN HAYES
CofO Issued 10/4/2022 MICHAEL SMITH
Permit Finaled 10/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/16/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 7/23/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/27/2021 CARLOS AGUILERA

Contact Information

Contractor L A Construction Group Inc; Lic. No.: 873259-B 18607 VENTURA BLVD #205      TARZANA, CA 91356
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2021 Approved DANIEL DREW
Deputy Drilled-In Anchors 10/1/2021 No Result Entered RAYMOND KEHOE
ELECTRICAL-Rough 10/7/2021 Not Ready for Inspection DANIEL DREW
Excavation/Setback/Form/Re-Bar 10/7/2021 Approved DANIEL DREW
PLUMBING-Rough 10/7/2021 Partial Approval DANIEL DREW
Underground Mechanical 10/7/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 10/28/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Conditional Approval ARAM AVEDISIAN
Underground Mechanical 10/29/2021 Approved CALEB MEISTER
BUILDING-Rough-Frame 11/5/2021 Approved DANIEL DREW
Green Building Rough 11/5/2021 Approved DANIEL DREW
ELECTRICAL-Rough 11/10/2021 Approved CALEB MEISTER
HVAC-Rough 11/10/2021 Corrections Issued CALEB MEISTER
PLUMBING-Rough 11/10/2021 Corrections Issued CALEB MEISTER
HVAC-Rough 11/16/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 11/16/2021 Partial Approval CALEB MEISTER
PLUMBING-Rough 11/16/2021 Approved CALEB MEISTER
Insulation 11/17/2021 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 11/17/2021 Partial Approval CALEB MEISTER
Shower Pan 11/17/2021 Approved CALEB MEISTER
Insulation 11/22/2021 Corrections Issued MISAEL ESPARZA
Insulation 11/30/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 12/6/2021 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 12/6/2021 Approved ASHLEY THOMPSON
Insulation 12/29/2021 Partial Approval JOHN KIDWELL
Drywall Nailing 1/4/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 3/10/2022 Corrections Issued MATT KELLERMAN
Final 3/10/2022 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 3/10/2022 Approved MATT KELLERMAN
Green Building Final 3/10/2022 Not Ready for Inspection MATT KELLERMAN
HVAC-Final 3/10/2022 Corrections Issued MATT KELLERMAN
PLUMBING-Final 3/10/2022 Corrections Issued MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 3/10/2022 Not Ready for Inspection MATT KELLERMAN
Final 3/21/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 3/24/2022 Corrections Issued MISAEL ESPARZA
Final 3/24/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 3/24/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/24/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 3/24/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/24/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Rec and Parks Fee Memo 3/24/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 4/8/2022 Corrections Issued MATT KELLERMAN
Final 4/8/2022 Corrections Issued MATT KELLERMAN
Green Building Final 4/8/2022 Approved MATT KELLERMAN
HVAC-Final 4/8/2022 Approved MATT KELLERMAN
PLUMBING-Final 4/8/2022 Approved MATT KELLERMAN
Service/Power Release 4/8/2022 Approved MATT KELLERMAN
Smoke Detectors 4/8/2022 Approved MATT KELLERMAN
Final 4/27/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 5/3/2022 Corrections Issued ARAM AVEDISIAN
Pre-Inspection 5/6/2022 No Access for Inspection MATT KELLERMAN
Final 7/5/2022 Corrections Issued JOHN HAYES
Final 9/19/2022 Not Ready for Inspection JOHN HAYES
Final 9/30/2022 OK to Issue CofO JOHN HAYES