6235 N CARTWRIGHT AVE 91606
Certificate Information: 6235 N CARTWRIGHT AVE 91606
- Application / Permit
- 21014-10000-01165
- Plan Check / Job No.
- B21LA04477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) garage and add 2nd floor to create a two story accessory dwelling unit per Ordinance LAMC 12.22A.33(b)(6)
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2021 | VU NGUYEN |
| Corrections Issued | 3/14/2021 | VU NGUYEN |
| Plan Check Approved | 8/27/2021 | VU NGUYEN |
| Issued | 9/10/2021 | APPLICANT |
| CofO in Progress | 10/3/2022 | JOHN HAYES |
| CofO Issued | 10/4/2022 | MICHAEL SMITH |
| Permit Finaled | 10/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/16/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/23/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | L A Construction Group Inc; Lic. No.: 873259-B | 18607 VENTURA BLVD #205 TARZANA, CA 91356 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2021 | Approved | DANIEL DREW |
| Deputy Drilled-In Anchors | 10/1/2021 | No Result Entered | RAYMOND KEHOE |
| ELECTRICAL-Rough | 10/7/2021 | Not Ready for Inspection | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 10/7/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 10/7/2021 | Partial Approval | DANIEL DREW |
| Underground Mechanical | 10/7/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 10/28/2021 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Conditional Approval | ARAM AVEDISIAN |
| Underground Mechanical | 10/29/2021 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/5/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 11/10/2021 | Approved | CALEB MEISTER |
| HVAC-Rough | 11/10/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 11/10/2021 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 11/16/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 11/16/2021 | Approved | CALEB MEISTER |
| Insulation | 11/17/2021 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | CALEB MEISTER |
| Shower Pan | 11/17/2021 | Approved | CALEB MEISTER |
| Insulation | 11/22/2021 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 11/30/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 12/6/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/6/2021 | Approved | ASHLEY THOMPSON |
| Insulation | 12/29/2021 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 1/4/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 3/10/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 3/10/2022 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 3/10/2022 | Approved | MATT KELLERMAN |
| Green Building Final | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Final | 3/10/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Final | 3/10/2022 | Corrections Issued | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 3/21/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/24/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/24/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Rec and Parks Fee Memo | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/8/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 4/8/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 4/8/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 4/8/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 4/8/2022 | Approved | MATT KELLERMAN |
| Service/Power Release | 4/8/2022 | Approved | MATT KELLERMAN |
| Smoke Detectors | 4/8/2022 | Approved | MATT KELLERMAN |
| Final | 4/27/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 5/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Inspection | 5/6/2022 | No Access for Inspection | MATT KELLERMAN |
| Final | 7/5/2022 | Corrections Issued | JOHN HAYES |
| Final | 9/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/30/2022 | OK to Issue CofO | JOHN HAYES |