10909 W MORRISON ST 1-10 91601
Certificate Information: 10909 W MORRISON ST 1-10 91601
- Application / Permit
- 21014-10000-01162
- Plan Check / Job No.
- B21LA04461
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan CREATE TWO ATTACHED ACCESSORY DWELLING UNITS PER STATE LAW GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 5/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | MICHAEL LOPEZ |
| Corrections Issued | 4/28/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 5/4/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/23/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/8/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 5/3/2022 | ARSALAN SHABESTARI |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 4/28/2023 | ROBERT DAVIS |
| Permit Finaled | 5/4/2023 | JEFFREY DURAN |
| CofO Issued | 5/4/2023 | JEFFREY DURAN |
| Permit Finaled | 5/4/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/22/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | DAGOVERTO GUERRERO |
| "Q" conditions | Cleared | 6/29/2021 | RUBEN VASQUEZ |
| Tenant Habitability Plan | Cleared | 3/7/2022 | MICHAEL SOTO |
| Green Code | Cleared | 4/10/2022 | MICHAEL LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schwartzberg,, Leo Joshua; Lic. No.: C51851 | 7547 SEDGEWICK CT WEST HILLS, CA 91304 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2022 | Approved | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 9/21/2022 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 9/22/2022 | Approved | ROBERT DAVIS |
| Structural Steel Frame | 9/22/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 11/3/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 11/3/2022 | Partial Approval | ROBERT DAVIS |
| Insulation | 11/18/2022 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 11/18/2022 | Approved | ROBERT DAVIS |
| Drywall Nailing | 11/30/2022 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 11/30/2022 | Approved | ROBERT DAVIS |
| Final | 3/15/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 3/15/2023 | Approved | ROBERT DAVIS |
| Green Building Rough | 3/15/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 3/15/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 3/15/2023 | Approved | ROBERT DAVIS |
| Final | 4/5/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 4/28/2023 | OK to Issue CofO | ROBERT DAVIS |