- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | TSE MING HUANG |
| Corrections Issued | 3/16/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 5/3/2021 | TSE MING HUANG |
| Plan Check Approved | 5/12/2021 | TSE MING HUANG |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Issued | 12/23/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | JOHNNY MIRANDA |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/16/2021 | PEDRO AYALA |
| Sewer availability | Cleared | 4/19/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/21/2021 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 4/21/2021 | DINAH GARIN |
Contact Information
| Contractor | G G Decor Inc; Lic. No.: 992323-B | 18800 AMAR RD SUITE C-1 WALNUT, CA 91789 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/19/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 3/2/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/2/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/11/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 3/11/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/21/2022 | Approved | JOHNNY MIRANDA |
| Gas Test | 3/21/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 3/21/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/21/2022 | Approved | JOHNNY MIRANDA |
| Sewer | 3/21/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | KENNETH NAGLE |
| Green Building Rough | 4/4/2022 | Approved | KENNETH NAGLE |
| Insulation | 4/4/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | KENNETH NAGLE |
| Drywall Nailing | 4/8/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 4/12/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/16/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 5/16/2022 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/18/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 5/18/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/13/2022 | Approved | JOHNNY MIRANDA |
| Final | 7/13/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 7/13/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 7/13/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 7/13/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 7/13/2022 | Approved | JOHNNY MIRANDA |
| Final | 8/22/2022 | OK to Issue CofO | JOHNNY MIRANDA |