1339 1/2 S MANSFIELD AVE 90019
Certificate Information: 1339 1/2 S MANSFIELD AVE 90019
- Application / Permit
- 21014-10000-01146
- Plan Check / Job No.
- B21LA04417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD A GROUND FLOOR AND 2ND STORY ADU ADDITION 1035 SF TO AN EXISTING 1-STORY 2-CAR GARAGE, PER LAMC 12.22 A.33(C) & (D).
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Metro
- Current Status
- Issued on 12/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/15/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/21/2021 | JASON HEALEY |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Applicant returned to address corrections | 6/7/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 9/9/2022 | CHUNG-WEN CHUANG |
| Issued | 12/13/2022 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/22/2021 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 6/25/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 9/12/2021 | RUEL COLE |
| Low Impact Development | Cleared | 1/18/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | JEANIE LAM |
Contact Information
| Architect | Lopez,, Craig Joseph; Lic. No.: C14263 | 155 GRANADA ST STE "L" CAMARILLO, CA 93010 |
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2023 | Approved | CALEB MEISTER |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 7/5/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 7/5/2023 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Approved | CALEB MEISTER |
| Footing/Foundation/Slab | 7/7/2023 | Approved | CALEB MEISTER |
| METHANE-Barrier | 7/7/2023 | Approved | CALEB MEISTER |
| METHANE-Subgrade | 7/7/2023 | Approved | CALEB MEISTER |
| Deputy Reinf. Concrete | 7/11/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 1/15/2025 | Conditional Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 2/24/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Sewer | 2/25/2025 | Approved | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Approved | ENRIQUE MIRELES |
| Gas Test | 4/2/2025 | No Access for Inspection | ROBERT CORNELL |
| PLUMBING-Rough | 4/2/2025 | No Access for Inspection | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Approved | LUIS CASTRO |
| Gas Test | 4/4/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 4/4/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 4/4/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 4/17/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/22/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 5/22/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 5/22/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/15/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 8/15/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/18/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 8/18/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/18/2025 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 9/5/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 9/5/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/17/2025 | Approved | DEVON JACKSON |
| ELECTRICAL-Final | 12/18/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 3/13/2026 | Corrections Issued | JUSTIN HAWLEY |
| Special/Order Compliance | 7/16/2026 | Corrections Issued | JUSTIN HAWLEY |