5218 N SUMNER AVE 90041
Certificate Information: 5218 N SUMNER AVE 90041
- Application / Permit
- 21014-10000-01143
- Plan Check / Job No.
- B21LA04410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY (20'-5" X 20'-7") ADDITION TO THE REAR OF (E) SFD.
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 11/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | RAMA DABADGE |
| Corrections Issued | 3/25/2021 | RAMA DABADGE |
| Plan Check Approved | 2/20/2022 | FARSHAD ALIMOHAMADI |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | CRAIG VAUGHAN |
| CofO in Progress | 11/7/2023 | CRAIG VAUGHAN |
| CofO Issued | 11/8/2023 | DEROLD HAUFF |
| Permit Finaled | 11/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/1/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | THOMAS LANG |
| Low Impact Development | Cleared | 10/15/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/21/2021 | ABEL CASILLAS |
Contact Information
| Contractor | G A Design Build; Lic. No.: 941130-B | 8449 EVEREST ST DOWNEY, CA 90242 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/3/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/8/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/15/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| MERV13>=Rough | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/22/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/15/2022 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 9/15/2022 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 9/15/2022 | Approved | AMY COLIN |
| Insulation | 9/20/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 9/26/2022 | Not Ready for Inspection | SCOTT FINNILA |
| Insulation | 9/26/2022 | Not Ready for Inspection | SCOTT FINNILA |
| Insulation | 9/29/2022 | No Access for Inspection | BRIAN SULLIVAN |
| Insulation | 10/7/2022 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 10/13/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 10/19/2022 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Drywall Nailing | 10/26/2022 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | CRAIG VAUGHAN |
| Final | 9/29/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 9/29/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/29/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 9/29/2023 | Corrections Issued | CRAIG VAUGHAN |
| MERV13>=Final | 9/29/2023 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 9/29/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/29/2023 | Approved | CRAIG VAUGHAN |
| Final | 10/10/2023 | Conditional Approval | CRAIG VAUGHAN |
| Final | 11/6/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 11/6/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/6/2023 | Approved | CRAIG VAUGHAN |