6614 S 2ND AVE 90043

Certificate Information: 6614 S 2ND AVE 90043

Application / Permit
21014-10000-01142
Plan Check / Job No.
B21LA04408
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED TWO CAR GARAGE INTO ADU (413 SQ FT) AND ADDITION (120 SQ FT) PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 JOSEPH RAFOLS
Corrections Issued 3/22/2021 JOSEPH RAFOLS
Plan Check Approved 8/26/2021 ADAM HEGAZI
Issued 9/8/2021 APPLICANT
Building Plans Picked Up 9/9/2021 APPLICANT
CofO in Progress 1/28/2022 HORACE FULTZ
Permit Finaled 5/4/2022 DEROLD HAUFF
CofO Issued 5/4/2022 DEROLD HAUFF
Permit Finaled 5/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/16/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 6/16/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/20/2021 CECILIO NAVARRO
Sewer availability Cleared 7/20/2021 CECILIO NAVARRO
Construction near power lines Cleared 8/10/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/14/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 9/14/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/20/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved FREDDIE RIVERA
Green Building Rough 10/15/2021 Not Ready for Inspection FREDDIE RIVERA
Deputy Wood Construction 10/20/2021 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 10/21/2021 No Access for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/28/2021 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 10/28/2021 Approved FREDDIE RIVERA
Green Building Rough 10/28/2021 Approved FREDDIE RIVERA
HVAC-Rough 10/28/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 10/28/2021 Corrections Issued FREDDIE RIVERA
HVAC-Rough 11/1/2021 Partial Approval FREDDIE RIVERA
Insulation 11/1/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/1/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 11/1/2021 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 11/4/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 11/4/2021 Approved FREDDIE RIVERA
Drywall Nailing 11/9/2021 Approved FREDDIE RIVERA
Pre-Inspection 11/12/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/20/2021 Approved FREDDIE RIVERA
Final 12/20/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 12/20/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 12/20/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 1/6/2022 Corrections Issued ANTHONY EGSON
Final 1/6/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 1/24/2022 Approved FREDDIE RIVERA
Final 1/24/2022 OK to Issue CofO FREDDIE RIVERA
HVAC-Final 1/24/2022 Approved FREDDIE RIVERA
MERV13>=Final 1/24/2022 Approved FREDDIE RIVERA
PLUMBING-Final 1/24/2022 Approved FREDDIE RIVERA