6614 S 2ND AVE 90043
Certificate Information: 6614 S 2ND AVE 90043
- Application / Permit
- 21014-10000-01142
- Plan Check / Job No.
- B21LA04408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED TWO CAR GARAGE INTO ADU (413 SQ FT) AND ADDITION (120 SQ FT) PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | JOSEPH RAFOLS |
| Corrections Issued | 3/22/2021 | JOSEPH RAFOLS |
| Plan Check Approved | 8/26/2021 | ADAM HEGAZI |
| Issued | 9/8/2021 | APPLICANT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| CofO in Progress | 1/28/2022 | HORACE FULTZ |
| Permit Finaled | 5/4/2022 | DEROLD HAUFF |
| CofO Issued | 5/4/2022 | DEROLD HAUFF |
| Permit Finaled | 5/4/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 8/10/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/14/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/20/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Deputy Wood Construction | 10/20/2021 | Conditional Approval | AMY COLIN |
| BUILDING-Rough-Frame | 10/21/2021 | No Access for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/28/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/28/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/28/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 10/28/2021 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/28/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 11/1/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 11/1/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/1/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/4/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/4/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/9/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 11/12/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/20/2021 | Approved | FREDDIE RIVERA |
| Final | 12/20/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 12/20/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 12/20/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 1/24/2022 | Approved | FREDDIE RIVERA |
| Final | 1/24/2022 | OK to Issue CofO | FREDDIE RIVERA |
| HVAC-Final | 1/24/2022 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 1/24/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 1/24/2022 | Approved | FREDDIE RIVERA |