14618 W MINNEHAHA ST 91345
Certificate Information: 14618 W MINNEHAHA ST 91345
- Application / Permit
- 21014-10000-01124
- Plan Check / Job No.
- B21LA04279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New 2nd Floor Addition to Existing 2-Car to be Converted to Detached ADU
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | JOE VO |
| Corrections Issued | 4/7/2021 | JOE VO |
| Quality Review Completed | 4/12/2021 | MICHAEL PEREZ |
| Plan Check Approved | 9/15/2021 | JOE VO |
| Issued | 9/21/2021 | APPLICANT |
| CofO in Progress | 7/29/2022 | JENNIFER RABUCHIN |
| CofO Issued | 8/3/2022 | DEROLD HAUFF |
| Permit Finaled | 8/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/12/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 9/9/2021 | SARAH YOUSSEF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/9/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 11/9/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 11/9/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/9/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 11/9/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/15/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 11/19/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/19/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 12/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 12/2/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 12/2/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 12/2/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| METHANE-Rough | 12/2/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 12/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 12/8/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/8/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 12/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 12/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 12/8/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 12/13/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/13/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/14/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 5/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 6/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/5/2022 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 7/5/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 7/5/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 7/5/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 7/5/2022 | Conditional Approval | MATT KELLERMAN |
| HVAC-Final | 7/5/2022 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Final | 7/5/2022 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | MATT KELLERMAN |
| Smoke Detectors | 7/5/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/11/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/11/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |