8549 W KYLE ST 91040

Certificate Information: 8549 W KYLE ST 91040

Application / Permit
21014-10000-01060
Plan Check / Job No.
B21LA04081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION AND REMODEL TO EXISTING RESIDENCE: ADDITION (22' x 27' IRREG) TO REAR OF RESIDENCE, ADD (6' X 6') TO SOUTHWEST CORNER. RECONSTRUCT FRONT PORCH. REMODEL KITCHEN, HALLWAY AND INTERIOR.
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 FARSHAD ALIMOHAMADI
Corrections Issued 3/10/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/6/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 4/21/2021 JESSE JIMENEZ
Issued 5/26/2021 APPLICANT
Building Plans Picked Up 5/27/2021 APPLICANT
CofO in Progress 3/15/2022 MATTHEW NELSON
Permit Finaled 6/11/2022 MICHAEL SMITH
CofO Issued 6/11/2022 MICHAEL SMITH
Permit Finaled 6/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/23/2021 JOHN TRIANTAFYLLOS
ZA Case Cleared 3/23/2021 LAUREN PADICK
ZI Cleared 3/23/2021 LAUREN PADICK
Roof/Waste drainage to street Cleared 3/25/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 4/5/2021 BARTON HOLMES

Contact Information

Architect Karabachian,, Sevak A; Lic. No.: C38632 3765 FAIRMEADE ROAD      PASADENA, CA 91107
Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2021 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 6/21/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval MATTHEW NELSON
PLUMBING-Rough 7/6/2021 Partial Approval MATTHEW NELSON
Sewer 7/6/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 8/24/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 8/24/2021 Partial Approval MATTHEW NELSON
Green Building Rough 8/24/2021 Approved MATTHEW NELSON
HVAC-Rough 8/24/2021 Approved MATTHEW NELSON
PLUMBING-Rough 8/24/2021 Approved MATTHEW NELSON
Wood Frame 8/24/2021 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 8/31/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/31/2021 Approved MATTHEW NELSON
Shower Pan 8/31/2021 Approved MATTHEW NELSON
Wood Frame 8/31/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Approved MATTHEW NELSON
Insulation 9/13/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/13/2021 Approved MATTHEW NELSON
Drywall Nailing 9/20/2021 Approved JUSTIN HAWLEY
Final 12/6/2021 Corrections Issued MATTHEW NELSON
Gas Test 12/6/2021 Approved MATTHEW NELSON
Green Building Final 12/6/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 12/6/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 2/9/2022 No Access for Inspection MATTHEW NELSON
Final 2/9/2022 Corrections Issued MATTHEW NELSON
HVAC-Final 2/9/2022 No Access for Inspection MATTHEW NELSON
PLUMBING-Final 2/9/2022 No Access for Inspection MATTHEW NELSON
ELECTRICAL-Final 2/15/2022 Corrections Issued DAVID MATSON
HVAC-Final 2/15/2022 Approved DAVID MATSON
PLUMBING-Final 2/15/2022 Approved DAVID MATSON
ELECTRICAL-Final 3/14/2022 Approved MATTHEW NELSON
Final 3/14/2022 OK to Issue CofO MATTHEW NELSON