526 N AVENUE 53 90042

Certificate Information: 526 N AVENUE 53 90042

Application / Permit
21014-10000-01039
Plan Check / Job No.
B21LA03988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of dwelling to create family room. Addition of half bathroom to bedroom. Roof deck over rear addition with spiral staircase.
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 FARSHAD ALIMOHAMADI
Corrections Issued 3/11/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 12/16/2021 RICARDO RAMIREZ
Building Plans Picked Up 12/17/2021 APPLICANT
Issued 6/23/2022 APPLICANT
CofO in Progress 6/27/2023 HAMIK HARTOUNIAN
Permit Finaled 7/8/2023 DEROLD HAUFF
CofO Issued 7/8/2023 DEROLD HAUFF
Permit Finaled 7/8/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/24/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/24/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/24/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/24/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/24/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 3/24/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/25/2021 WALLIE JONG
Grading Pre-Inspection Cleared 4/1/2021 PATRICK MISCHLICH
HPOZ Cleared 4/23/2021 KATIE DEBIASE
Miscellaneous Cleared 4/23/2021 KATIE DEBIASE
Low Impact Development Cleared 12/8/2021 TA ANH

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/21/2022 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/21/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/25/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/25/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 7/25/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/5/2022 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/30/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 9/30/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 9/30/2022 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 10/4/2022 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Approved HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 10/6/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/21/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/16/2022 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/16/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/29/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/29/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/21/2022 Approved HAMIK HARTOUNIAN
Insulation 12/21/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/23/2023 Partial Approval HAMIK HARTOUNIAN
Pre-Inspection 2/13/2023 Partial Inspection HAMIK HARTOUNIAN
Final 3/23/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/23/2023 Approved HAMIK HARTOUNIAN
Green Building Final 3/23/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 3/23/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved SCOTT FINNILA
Final 6/2/2023 OK to Issue CofO HAMIK HARTOUNIAN