5346 W SANCHEZ DR 90008
Certificate Information: 5346 W SANCHEZ DR 90008
- Application / Permit
- 21014-10000-01028
- Plan Check / Job No.
- B21LA03941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 1075 SF TO EXISTING SFD
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | ZAW HAN |
| Corrections Issued | 3/30/2021 | ZAW HAN |
| Quality Review Completed | 4/5/2021 | KEN GILL |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| Applicant returned to address corrections | 6/28/2021 | ZAW HAN |
| Applicant returned to address corrections | 1/31/2022 | ZAW HAN |
| Applicant returned to address corrections | 4/15/2022 | ZAW HAN |
| Plan Check Approved | 5/3/2022 | ZAW HAN |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 4/7/2026 | LUIS CASTRO |
| CofO Issued | 4/9/2026 | DEROLD HAUFF |
| Permit Finaled | 4/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/23/2021 | BRIAN MILLER |
| CPC | Cleared | 6/17/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 3/2/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/16/2022 | WALLIE JONG |
| Sewer availability | Cleared | 3/22/2022 | WALLIE JONG |
| GPI Written Notices | Cleared | 4/6/2022 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2023 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 5/4/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/14/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/25/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/14/2023 | Approved | ANTHONY EGSON |
| Deputy Steel/Welding | 8/28/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | No Access for Inspection | ANTHONY EGSON |
| Special/Order Compliance | 9/25/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/3/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 11/6/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 11/6/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/8/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/14/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/28/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/18/2024 | Approved | ANTHONY EGSON |
| Insulation | 1/24/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/22/2025 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 9/22/2025 | Approved | BRENDAN MORELLI |
| Final | 9/22/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 9/22/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 9/22/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 9/22/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/29/2025 | Corrections Issued | LUIS CASTRO |
| Final | 12/29/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 12/29/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Approved | LUIS CASTRO |
| ELECTRICAL-Final | 2/12/2026 | Approved | LUIS CASTRO |
| HVAC-Final | 2/12/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 2/12/2026 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/6/2026 | Approved | LUIS CASTRO |
| Final | 4/6/2026 | OK to Issue CofO | LUIS CASTRO |