13028 W BURTON ST 91605
Certificate Information: 13028 W BURTON ST 91605
- Application / Permit
- 21014-10000-01027
- Plan Check / Job No.
- B21LA03932
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) rec room to new ADU with 154 sf addition per WFPP.
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | JOE VO |
| Corrections Issued | 3/26/2021 | JOE VO |
| Quality Review Completed | 4/1/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/7/2021 | JOE VO |
| Plan Check Approved | 6/25/2021 | JOE VO |
| Plan Check Approved | 7/6/2021 | JOE VO |
| Issued | 7/6/2021 | APPLICANT |
| CofO in Progress | 7/6/2022 | GREGG CUMMINGS |
| CofO Issued | 7/16/2022 | MICHAEL SMITH |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/21/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/22/2021 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/1/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/9/2021 | Corrections Issued | GREGG CUMMINGS |
| Pre-Inspection | 12/17/2021 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 2/28/2022 | Partial Approval | GREGG CUMMINGS |
| Structural Steel Frame | 3/15/2022 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/29/2022 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/29/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/29/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 4/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/28/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/28/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/5/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/5/2022 | Approved | GREGG CUMMINGS |
| Insulation | 5/11/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 5/16/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/24/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/24/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/24/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 6/29/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/5/2022 | Approved | GREGG CUMMINGS |
| Final | 7/5/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 7/5/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/5/2022 | Approved | GREGG CUMMINGS |