878 N OREO PL 90272
Certificate Information: 878 N OREO PL 90272
- Application / Permit
- 21014-10000-01026
- Plan Check / Job No.
- B21LA03931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION TO EXISTING 2-STORY SFD. NEW WINDOWS/DOORS. INTERIOR REMODEL THROUGHOUT PER PLAN
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | KHEDER ALRAZAA |
| Corrections Issued | 3/16/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 3/22/2021 | JASON HEALEY |
| Plan Check Approved | 8/23/2021 | KHEDER ALRAZAA |
| Issued | 9/1/2021 | APPLICANT |
| CofO in Progress | 2/8/2023 | BRENDAN LOONEY |
| No Progress | 2/10/2023 | BRENDAN LOONEY |
| CofO in Progress | 2/14/2023 | RONALD MYRICK |
| Permit Finaled | 2/14/2023 | RONALD MYRICK |
| CofO Issued | 2/14/2023 | RONALD MYRICK |
| Permit Finaled | 2/14/2023 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/6/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 4/6/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 4/6/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 4/6/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 4/6/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | TRACY TATE |
| Permit | Cleared | 4/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/11/2021 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 7/15/2021 | DANIEL CORONADO |
| ZI | Cleared | 7/15/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 8/18/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/19/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 8/23/2021 | KHEDER ALRAZAA |
Contact Information
| Contractor | Miller Construction & Development Inc; Lic. No.: 878221-B | 906 EMBURY STREET PACIFIC PALISADES, CA 90272 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/7/2021 | Partial Inspection | JUAN VALENZUELA |
| Pre-Inspection | 10/1/2021 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 11/1/2021 | Partial Approval | ANDREW NAVE |
| Deputy Other (see comments) | 11/4/2021 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/3/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/17/2021 | Partial Inspection | ANDREW NAVE |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/20/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Approval | ANDREW NAVE |
| Deputy Other (see comments) | 3/31/2022 | Approved | MICHAEL PELHAM |
| Deputy Wood Construction | 4/1/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/8/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/2/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 5/2/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/4/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/5/2022 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 5/5/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/5/2022 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/11/2022 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | ANDREW NAVE |
| Insulation | 5/19/2022 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 6/1/2022 | Approved | ANDREW NAVE |
| Insulation | 6/1/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 6/13/2022 | Not Ready for Inspection | ANDREW NAVE |
| Underground Mechanical | 6/13/2022 | Approved | ANDREW NAVE |
| Shower Pan | 6/15/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/11/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 9/7/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Gas Test | 9/7/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/18/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/22/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 11/22/2022 | Approved | BRENDAN LOONEY |
| Service/Power Release | 11/22/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 11/28/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 11/30/2022 | Approved | BRENDAN LOONEY |
| Final | 12/8/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 12/8/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 12/8/2022 | Approved | BRENDAN LOONEY |
| Final | 12/16/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 2/7/2023 | OK to Issue CofO | BRENDAN LOONEY |