1935 W 42ND ST 90062

Certificate Information: 1935 W 42ND ST 90062

Application / Permit
21014-10000-00994
Plan Check / Job No.
B21LA03804
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) one-story detached garage to ADU per LAMC 12.22 A.33 (c),(d) with one story addition. All work per WFPP.
Permit Issued
Issued on 6/8/2022
Issuing Office
Current Status
CofO Issued on 4/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 AARON COSTA
Corrections Issued 3/11/2021 AARON COSTA
Quality Review Completed 4/29/2022 CHRISTOPHER KOMANCHECK
Plan Check Approved 5/3/2022 GEORGE ALVAREZ
Issued 6/8/2022 APPLICANT
Building Plans Picked Up 6/14/2022 APPLICANT
CofO in Progress 4/7/2023 STUART CHAPMAN
Permit Finaled 4/8/2023 DEROLD HAUFF
Permit Finaled 4/8/2023 DEROLD HAUFF
CofO Issued 4/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/11/2021 WALLIE JONG
Construction near power lines Cleared 8/5/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/7/2021 WALLIE JONG
Sewer availability Cleared 9/7/2021 WALLIE JONG
Low Impact Development Cleared 3/8/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 3/18/2022 STEVE MELGAR
Hold Cleared 6/17/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/24/2022 Approved SABAS ALONSO
Underground Mechanical 6/24/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 7/5/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/26/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval SABAS ALONSO
Green Building Rough 9/7/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 9/7/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/19/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Approved SABAS ALONSO
PLUMBING-Rough 9/19/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 9/19/2022 Partial Approval SABAS ALONSO
HVAC-Rough 9/29/2022 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 9/29/2022 Partial Approval SABAS ALONSO
Underground Mechanical 9/29/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/11/2022 Approved RYAN SALAZAR
Green Building Rough 10/11/2022 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 10/11/2022 Approved RYAN SALAZAR
Wood Frame 10/11/2022 Approved RYAN SALAZAR
Insulation 10/20/2022 Partial Approval SABAS ALONSO
Drywall Nailing 11/2/2022 Approved SABAS ALONSO
Final 2/1/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 2/1/2023 Approved ALIZAH MAYAGOITIA
Final 3/21/2023 Corrections Issued STUART CHAPMAN
Green Building Final 3/21/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready STUART CHAPMAN
ELECTRICAL-Final 4/7/2023 Approved STUART CHAPMAN
Final 4/7/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 4/7/2023 Approved STUART CHAPMAN
PLUMBING-Final 4/7/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Approved STUART CHAPMAN