1251 N TOWER GROVE DR 90210

Certificate Information: 1251 N TOWER GROVE DR 90210

Application / Permit
21014-10000-00993
Plan Check / Job No.
B21LA03802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 DANIEL YIP
Corrections Issued 3/31/2021 DANIEL YIP
Quality Review Completed 4/3/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/10/2021 DANIEL YIP
Plan Check Approved 8/13/2021 DANIEL YIP
Issued 9/10/2021 APPLICANT
Building Plans Picked Up 9/14/2021 APPLICANT
CofO in Progress 12/24/2022 MICHAEL PELHAM
Permit Finaled 12/27/2022 DANIEL ORRANTE
CofO Issued 12/27/2022 DANIEL ORRANTE
Permit Finaled 12/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 4/27/2021 LOUIS ORTEGA
BHO/Hillside ordinance Cleared 4/30/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 4/30/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 4/30/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 4/30/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 4/30/2021 DINAH GARIN
Sewer availability Cleared 4/30/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/4/2021 DINAH GARIN

Contact Information

Architect , ; Lic. No.: C36197 1692 SIRRINE DRIVE      SANTA ANA, CA 92705
Contractor Hamilton Brothers Construction Inc; Lic. No.: 1025301-B P O BOX 801844      SANTA CLARITA, CA 91381
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/4/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 6/13/2022 Approved MICHAEL PELHAM
Drywall Nailing 6/13/2022 Approved MICHAEL PELHAM
Final 6/13/2022 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 6/13/2022 Approved MICHAEL PELHAM
Green Building Final 6/13/2022 Approved MICHAEL PELHAM
Green Building Rough 6/13/2022 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Approved MICHAEL PELHAM
Smoke Detectors 6/13/2022 Approved MICHAEL PELHAM
Final 11/23/2022 Conditional Approval MICHAEL PELHAM