1639 1/2 W 84TH ST 90047

Certificate Information: 1639 1/2 W 84TH ST 90047

Application / Permit
21014-10000-00990
Plan Check / Job No.
B21LA03801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO A.D.U. PER STATE LAW. INCLUDES ADDITION. CONSTRUCTION PER W.F.P.P.
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 LAWRENCE QUIRANTE
Corrections Issued 3/9/2021 LAWRENCE QUIRANTE
Plan Check Approved 9/21/2021 ADAM HEGAZI
Issued 10/13/2021 APPLICANT
Building Plans Picked Up 10/14/2021 APPLICANT
CofO in Progress 3/30/2023 ENRIQUE MIRELES
CofO in Progress 3/30/2023 ENRIQUE MIRELES
Permit Finaled 5/16/2023 DEROLD HAUFF
CofO Issued 5/16/2023 DEROLD HAUFF
Permit Finaled 5/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 4/8/2021 JASON SHEETS
Address approval Cleared 4/22/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 4/22/2021 JEANIE LAM
Sewer availability Cleared 4/22/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/27/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Footing/Foundation/Slab 12/16/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 12/16/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 12/21/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 12/21/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/1/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/31/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/31/2022 Approved ENRIQUE MIRELES
Green Building Rough 3/31/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/31/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/6/2022 Approved ENRIQUE MIRELES
Insulation 5/18/2022 Approved ENRIQUE MIRELES
Wood Frame 5/18/2022 Approved ENRIQUE MIRELES
Drywall Nailing 6/3/2022 Approved ENRIQUE MIRELES
Final 10/24/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 10/24/2022 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/24/2022 Partial Inspection FREDDIE RIVERA
Underground Mechanical 10/24/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Final 1/18/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 1/23/2023 Approved ENRIQUE MIRELES
Final 2/28/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/28/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/28/2023 Approved ENRIQUE MIRELES
Final 3/7/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 3/7/2023 Approved ENRIQUE MIRELES