6506 N GERALD AVE 91406
Certificate Information: 6506 N GERALD AVE 91406
- Application / Permit
- 21014-10000-00967
- Plan Check / Job No.
- B21LA03698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING FOR MASTER BEDROOM, BATH AND WALK-IN CLOSET.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2021 | GEORGE ALVAREZ |
| Corrections Issued | 5/19/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 6/22/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 6/22/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 6/22/2021 | GEORGE ALVAREZ |
| Issued | 6/22/2021 | APPLICANT |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| CofO in Progress | 6/8/2022 | ALAN MORELOS |
| Permit Finaled | 6/8/2022 | MICHAEL SMITH |
| CofO Issued | 6/8/2022 | MICHAEL SMITH |
| Permit Finaled | 6/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/4/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | A A A All Star Construction Inc; Lic. No.: 1018926-B | 12500 RIVERSIDE DRIVE 201A VALLEY VILLAGE, CA 91607 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 8/23/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 8/23/2021 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 8/26/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 10/18/2021 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/12/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 11/12/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/12/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/12/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/12/2021 | Approved | RAUL OLAGI |
| Insulation | 11/23/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 12/1/2021 | Approved | ALAN MORELOS |
| Shower Pan | 12/1/2021 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | ALAN MORELOS |
| Shower Pan | 12/7/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 2/28/2022 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 2/28/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 6/7/2022 | Approved | ALAN MORELOS |
| Final | 6/7/2022 | OK to Issue CofO | ALAN MORELOS |
| Green Building Final | 6/7/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 6/7/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 6/7/2022 | Approved | ALAN MORELOS |
| PLUMBING-Final | 6/7/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | ALAN MORELOS |
| Service/Power Release | 6/7/2022 | Approved | ALAN MORELOS |
| Smoke Detectors | 6/7/2022 | Approved | ALAN MORELOS |