13066 W DEBELL ST 91331

Certificate Information: 13066 W DEBELL ST 91331

Application / Permit
21014-10000-00962
Plan Check / Job No.
B21LA03637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED OPEN PATIO, ENCLOSED PATIO AND DAMAGE ROOF TO BE REPAIR IN GARAGE AT EXISTING 1 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER ENGINEER DESIGN
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 8/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 AUNG SOE
Corrections Issued 3/10/2021 AUNG SOE
Building Plans Picked Up 3/12/2021 APPLICANT
Applicant returned to address corrections 5/5/2021 AUNG SOE
Applicant returned to address corrections 10/6/2021 RICARDO RAMIREZ
Plan Check Approved 10/19/2021 RICARDO RAMIREZ
Issued 11/4/2021 APPLICANT
CofO in Progress 8/3/2022 MICHEL ABAJAN
Permit Finaled 8/9/2022 DEROLD HAUFF
CofO Issued 8/9/2022 DEROLD HAUFF
Permit Finaled 8/9/2022 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 3/17/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 4/26/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/29/2021 JOHN CONNEALLY
Low Impact Development Cleared 9/22/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/13/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Valley Green Inc; Lic. No.: 844306-B 2648 FAIR OAKS AVENUE      ALTADENA, CA 91001
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/5/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 1/5/2022 Approved MICHEL ABAJAN
Gas Test 2/16/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 2/16/2022 Approved MICHEL ABAJAN
Wood Frame 2/16/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/11/2022 Approved MICHEL ABAJAN
HVAC-Rough 3/11/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/11/2022 Approved MICHEL ABAJAN
Insulation 3/16/2022 Approved MICHEL ABAJAN
Drywall Nailing 3/25/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/25/2022 Approved MICHEL ABAJAN
Shower Pan 3/25/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/11/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/25/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/25/2022 Approved MICHEL ABAJAN
Final 5/25/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 5/25/2022 Approved MICHEL ABAJAN
Green Building Rough 5/25/2022 Approved MICHEL ABAJAN
HVAC-Final 5/25/2022 Approved MICHEL ABAJAN
MERV13>=Final 5/25/2022 Approved MICHEL ABAJAN
MERV13>=Rough 5/25/2022 Approved MICHEL ABAJAN
PLUMBING-Final 5/25/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/25/2022 Approved MICHEL ABAJAN
Final 8/3/2022 OK to Issue CofO MICHEL ABAJAN