2758 S WESTGATE AVE 90064
Certificate Information: 2758 S WESTGATE AVE 90064
- Application / Permit
- 21014-10000-00951
- Plan Check / Job No.
- B21LA03585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 294 SQFT ADDITION TO (E) SFD CONSISTING OF A MASTER SUITE BED/BATH, WALKIN CLOSET AND ENLARGEING OF A 2ND BEDROOM. NO INCREASE IN BED/BATH COUNT
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | RAHEL BEYENE |
| Corrections Issued | 3/5/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 4/7/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 4/19/2021 | TSE MING HUANG |
| Plan Check Approved | 5/12/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 5/14/2021 | APPLICANT |
| Issued | 5/19/2021 | APPLICANT |
| CofO in Progress | 1/19/2023 | JOHNNY MIRANDA |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
| CofO Issued | 1/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/25/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/26/2021 | DINAH GARIN |
| Specific Plan | Cleared | 4/11/2021 | EDUARDO HERMOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Tzuoh-Jaw; Lic. No.: S5002 | 9352 LANGSTON ST RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2021 | Corrections Issued | ANDREW BEELI |
| Service/Power Release | 6/11/2021 | Approved | ANDREW BEELI |
| Footing/Foundation/Slab | 6/24/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 7/1/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 8/12/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 8/12/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 8/18/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 8/18/2021 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 8/18/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/31/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/12/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/12/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/12/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 11/12/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 11/12/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/12/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 11/12/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/24/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/24/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 11/24/2021 | Approved | JOHNNY MIRANDA |
| Final | 9/15/2022 | Conditional Approval | JOHNNY MIRANDA |
| Final | 1/18/2023 | OK to Issue CofO | JOHNNY MIRANDA |