2758 S WESTGATE AVE 90064

Certificate Information: 2758 S WESTGATE AVE 90064

Application / Permit
21014-10000-00951
Plan Check / Job No.
B21LA03585
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
294 SQFT ADDITION TO (E) SFD CONSISTING OF A MASTER SUITE BED/BATH, WALKIN CLOSET AND ENLARGEING OF A 2ND BEDROOM. NO INCREASE IN BED/BATH COUNT
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
CofO Issued on 1/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 RAHEL BEYENE
Corrections Issued 3/5/2021 RAHEL BEYENE
Applicant returned to address corrections 4/7/2021 SINA KHOSRAVI
Applicant returned to address corrections 4/19/2021 TSE MING HUANG
Plan Check Approved 5/12/2021 FERNANDO FLORES
Building Plans Picked Up 5/14/2021 APPLICANT
Issued 5/19/2021 APPLICANT
CofO in Progress 1/19/2023 JOHNNY MIRANDA
Permit Finaled 1/26/2023 DANIEL ORRANTE
CofO Issued 1/26/2023 DANIEL ORRANTE
Permit Finaled 1/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 3/25/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/26/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/26/2021 DINAH GARIN
Specific Plan Cleared 4/11/2021 EDUARDO HERMOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Tzuoh-Jaw; Lic. No.: S5002 9352 LANGSTON ST      RANCHO CUCAMONGA, CA 91730

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2021 Corrections Issued ANDREW BEELI
Service/Power Release 6/11/2021 Approved ANDREW BEELI
Footing/Foundation/Slab 6/24/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 7/1/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 7/1/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 8/12/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Approved ANDREW NAVE
PLUMBING-Rough 8/12/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 8/18/2021 Partial Approval OGANES TARAKHCHYAN
Service/Power Release 8/18/2021 Approved OGANES TARAKHCHYAN
Wood Frame 8/18/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 8/24/2021 Approved OGANES TARAKHCHYAN
Insulation 8/24/2021 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/24/2021 Approved OGANES TARAKHCHYAN
Shower Pan 8/24/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/31/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/12/2021 Approved JOHNNY MIRANDA
Drywall Nailing 11/12/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 11/12/2021 Corrections Issued JOHNNY MIRANDA
Final 11/12/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 11/12/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 11/12/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 11/12/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 11/24/2021 Approved JOHNNY MIRANDA
Final 11/24/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 11/24/2021 Approved JOHNNY MIRANDA
Final 9/15/2022 Conditional Approval JOHNNY MIRANDA
Final 1/18/2023 OK to Issue CofO JOHNNY MIRANDA