1749 W LEIGHTON AVE 90062
Certificate Information: 1749 W LEIGHTON AVE 90062
- Application / Permit
- 21014-10000-00948
- Plan Check / Job No.
- B21LA03577
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage to adu and addition per WFPP (1200 sf max) per ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | AUNG SOE |
| Corrections Issued | 3/16/2021 | AUNG SOE |
| Applicant returned to address corrections | 5/25/2021 | CRISTINA SALAZAR |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| Plan Check Approved | 3/14/2023 | KHUONG TRUONG |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 1/27/2025 | SABAS ALONSO |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
| CofO Issued | 1/28/2025 | DEROLD HAUFF |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/4/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 9/17/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 9/17/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/28/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/26/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/30/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 10/3/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 10/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/1/2024 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/1/2024 | Approved | JOAQUIN GREENOUGH |
| Sewer | 11/1/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 11/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 11/18/2024 | Approved | JOSE MACIAS |
| Sewer | 11/18/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 11/22/2024 | Approved | SABAS ALONSO |
| Insulation | 11/22/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 11/22/2024 | Approved | SABAS ALONSO |
| Shower Pan | 11/22/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/27/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 11/27/2024 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 12/3/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/3/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/10/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 12/19/2024 | Approved | SABAS ALONSO |
| Final | 1/10/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/10/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 1/10/2025 | Approved | SABAS ALONSO |
| Final | 1/21/2025 | OK to Issue CofO | SABAS ALONSO |