1677 S VICTORIA AVE 90019
Certificate Information: 1677 S VICTORIA AVE 90019
- Application / Permit
- 21014-10000-00942
- Plan Check / Job No.
- B21LA03556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED 2-CAR CARPORT TO (N) ATTACHED 2-CAR GARAGE AND (N) 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | DANIEL YIP |
| Corrections Issued | 3/12/2021 | DANIEL YIP |
| Quality Review Completed | 3/19/2021 | JASON HEALEY |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Applicant returned to address corrections | 9/21/2021 | DANIEL YIP |
| Applicant returned to address corrections | 2/15/2022 | DANIEL YIP |
| Applicant returned to address corrections | 6/30/2022 | DANIEL YIP |
| Plan Check Approved | 7/25/2023 | DANIEL YIP |
| No Progress | 7/25/2023 | DANIEL YIP |
| Plan Check Approved | 8/30/2023 | DANIEL YIP |
| Issued | 9/13/2023 | APPLICANT |
| CofO in Progress | 3/17/2026 | JUSTIN HAWLEY |
| Permit Finaled | 3/18/2026 | DEROLD HAUFF |
| CofO Issued | 3/18/2026 | DEROLD HAUFF |
| Permit Finaled | 3/18/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 3/26/2021 | AMANDA KAINER |
| Miscellaneous | Cleared | 2/10/2022 | AMANDA KAINER |
| Sewer availability | Cleared | 5/31/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 8/21/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | TERRY PHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Merritt,, Leonid; Lic. No.: C38496 | 1255 DANIELS DRIVE LOS ANGELES, CA 90035 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/12/2024 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 11/20/2024 | Corrections Issued | BRENDAN MORELLI |
| METHANE-Barrier | 11/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Subgrade | 11/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Structural Steel Frame | 11/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/10/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Barrier | 12/10/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Subgrade | 12/10/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 3/3/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 3/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 3/3/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/3/2025 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 4/9/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 4/9/2025 | Conditional Approval | WILLIAM SIERRA |
| METHANE-Rough | 4/9/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 4/9/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 4/17/2025 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/25/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/25/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/9/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/21/2025 | Partial Approval | ALEX COLIN |
| Insulation | 5/21/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 5/27/2025 | Partial Approval | ALEX COLIN |
| PLUMBING-Rough | 7/3/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JOSH MEISTER |
| Final | 11/10/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 11/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 11/10/2025 | Approved | JUSTIN HAWLEY |
| Final | 2/2/2026 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 3/2/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/2/2026 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/2/2026 | Approved | JUSTIN HAWLEY |
| Final | 3/17/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| METHANE-Final | 3/17/2026 | Approved | JUSTIN HAWLEY |