5216 N SUMNER AVE 90041

Certificate Information: 5216 N SUMNER AVE 90041

Application / Permit
21014-10000-00921
Plan Check / Job No.
B21LA03453
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan. Ground floor addition to an existing detached garage and conversion of entire building into an ADU per ordinance 186,481.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 HELEN NGUYEN
Corrections Issued 3/4/2021 HELEN NGUYEN
Applicant returned to address corrections 4/15/2021 CARLOS MONTES
Plan Check Approved 4/19/2021 HELEN NGUYEN
Issued 4/28/2021 APPLICANT
CofO in Progress 2/21/2024 CRAIG VAUGHAN
Permit Finaled 2/28/2024 DEROLD HAUFF
CofO Issued 2/28/2024 DEROLD HAUFF
Permit Finaled 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/15/2021 RENZ SORIANO
Hold Cleared 3/15/2021 JASON SHEETS
Roof/Waste drainage to street Cleared 3/15/2021 RENZ SORIANO
Address approval Cleared 3/17/2021 RENZ SORIANO
Sewer availability Cleared 3/30/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 4/5/2021 BARTON HOLMES

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2021 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/24/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/3/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/29/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/1/2021 Approved CRAIG VAUGHAN
Green Building Rough 10/1/2021 Approved CRAIG VAUGHAN
MERV13>=Rough 10/1/2021 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 10/1/2021 Approved CRAIG VAUGHAN
Insulation 10/13/2021 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 10/13/2021 Approved CHARLES BOGHOSKHAN
Drywall Nailing 10/26/2021 Approved CHARLES BOGHOSKHAN
Final 9/29/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/29/2023 Approved CRAIG VAUGHAN
MERV13>=Final 9/29/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/29/2023 Approved CRAIG VAUGHAN
Final 10/10/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 10/10/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 2/20/2024 Approved CRAIG VAUGHAN
Final 2/20/2024 OK to Issue CofO CRAIG VAUGHAN