130 E 46TH ST 90011
Certificate Information: 130 E 46TH ST 90011
- Application / Permit
- 21014-10000-00898
- Plan Check / Job No.
- B21LA03406
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE INTO A.D.U. PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/11/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/14/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| Issued | 9/27/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | SHAVONNE ESPINOZA |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
| CofO Issued | 2/14/2023 | DEROLD HAUFF |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/24/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/12/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 11/5/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/16/2021 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 12/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 12/6/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 12/22/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 1/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/14/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Rough | 1/14/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Insulation | 1/24/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 1/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 2/4/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/4/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 2/22/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 3/10/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 3/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/15/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 3/18/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/18/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 7/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/8/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 8/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/17/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 9/7/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 9/15/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Final | 9/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Wood Frame | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/29/2022 | OK to Issue CofO | SHAVONNE ESPINOZA |