7042 S 2ND AVE 90043
Certificate Information: 7042 S 2ND AVE 90043
- Application / Permit
- 21014-10000-00880
- Plan Check / Job No.
- B21LA03372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 2-CAR GARAGE AND ADJACENT SUNSHADE ROOM INTO ADU.
- Permit Issued
- Issued on 10/9/2021
- Issuing Office
- Current Status
- CofO Issued on 4/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/14/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/8/2021 | FERNANDO FLORES |
| Plan Check Approved | 8/3/2021 | SAMUEL GONZALEZ |
| Issued | 10/9/2021 | APPLICANT |
| Building Plans Picked Up | 10/19/2021 | APPLICANT |
| CofO in Progress | 4/4/2023 | ENRIQUE MIRELES |
| CofO in Progress | 4/17/2023 | ENRIQUE MIRELES |
| CofO in Progress | 4/19/2023 | ENRIQUE MIRELES |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
| CofO Issued | 4/22/2023 | DEROLD HAUFF |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | JUAN ASHTON |
| Sewer availability | Cleared | 4/30/2021 | JUAN ASHTON |
| Construction near power lines | Cleared | 5/14/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/25/2021 | KURT CORRAL |
Contact Information
| Contractor | Scales Zerik; Lic. No.: 1012586-B | 4922 WEST BLVD LOS ANGELES, CA 90043 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 12/20/2021 | Corrections Issued | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 12/22/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/23/2021 | Conditional Approval | FREDDIE RIVERA |
| Sewer | 12/23/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/8/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 5/9/2022 | Corrections Issued | HORACE FULTZ |
| HVAC-Rough | 5/27/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Reinforced Concrete Frame | 6/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 8/3/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/3/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/17/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 8/17/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/17/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/19/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/19/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 8/29/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/9/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/9/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/9/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/21/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/21/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/21/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/21/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Reinforced Masonry Frame | 12/21/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Final | 1/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 2/1/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 2/13/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Final | 4/18/2023 | OK to Issue CofO | ENRIQUE MIRELES |