2628 S KERCKHOFF AVE 90731
Certificate Information: 2628 S KERCKHOFF AVE 90731
- Application / Permit
- 21014-10000-00879
- Plan Check / Job No.
- B21LA03371
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY [265sf] addition to rear of home. ADD new master bed with full bathroom.
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2021 | JESSE JIMENEZ |
| Corrections Issued | 3/3/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 8/5/2021 | JESSE JIMENEZ |
| Plan Check Approved | 9/3/2021 | FERNANDO FLORES |
| Issued | 10/12/2021 | APPLICANT |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| CofO in Progress | 3/5/2022 | ANSON MAGLASANG |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/7/2021 | ERIK BEASLEY |
| Specific Plan | Cleared | 4/7/2021 | JEANALEE OBERGFELL |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 4/16/2021 | BRIAN MILLER |
| Coastal Zone | Cleared | 8/19/2021 | TERRI OSBORNE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2021 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 10/25/2021 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 11/29/2021 | Conditional Approval | ANSON MAGLASANG |
| Special/Order Compliance | 11/29/2021 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/9/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 12/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 12/16/2021 | Partial Approval | JOHN KLARIN |
| Wood Frame | 12/16/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/29/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 12/29/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 12/29/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Partial Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 1/4/2022 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 1/4/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/14/2022 | Conditional Approval | ANSON MAGLASANG |
| Green Building Rough | 1/14/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/14/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 1/20/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/20/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Drywall Nailing | 1/24/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 2/8/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | ANSON MAGLASANG |
| Final | 3/3/2022 | OK to Issue CofO | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/3/2022 | Approved | ANSON MAGLASANG |
| Green Building Final | 3/3/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 3/3/2022 | Approved | ANSON MAGLASANG |