5307 S 8TH AVE 90043

Certificate Information: 5307 S 8TH AVE 90043

Application / Permit
21014-10000-00875
Plan Check / Job No.
B21LA03346
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition to rear of dwelling to create additional bedroom.
Permit Issued
Issued on 12/31/2021
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/3/2021 JESSE JIMENEZ
Corrections Issued 3/8/2021 JESSE JIMENEZ
Applicant returned to address corrections 8/13/2021 TSE MING HUANG
Applicant returned to address corrections 8/31/2021 JESSE JIMENEZ
Plan Check Approved 12/21/2021 RICARDO RAMIREZ
Issued 12/31/2021 APPLICANT
Building Plans Picked Up 1/3/2022 APPLICANT
CofO in Progress 8/4/2022 ANTHONY EGSON
CofO Issued 8/26/2022 DEROLD HAUFF
Permit Finaled 8/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 3/5/2021 JASON SHEETS
Eng Process Fee Ord 176,300 Cleared 9/9/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 9/9/2021 JEANIE LAM
Sewer availability Cleared 9/9/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2022 Corrections Issued SHAVONNE ESPINOZA
Deputy Drilled-In Anchors 1/19/2022 Conditional Approval ADAM ESCOTO
Footing/Foundation/Slab 1/21/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 1/31/2022 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/2/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 4/7/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 4/7/2022 Approved ANTHONY EGSON
Green Building Rough 4/7/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/20/2022 Approved ANTHONY EGSON
Insulation 4/26/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/26/2022 Approved ANTHONY EGSON
Drywall Nailing 5/18/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 6/16/2022 Partial Approval ANTHONY EGSON
HVAC-Final 6/16/2022 Partial Approval ANTHONY EGSON
Final 7/18/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/18/2022 Approved ANTHONY EGSON
Green Building Final 7/18/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 7/18/2022 Approved ANTHONY EGSON
Final 8/2/2022 OK to Issue CofO ANTHONY EGSON
Green Building Final 8/2/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved ANTHONY EGSON