3416 W MADERA AVE 90039
Certificate Information: 3416 W MADERA AVE 90039
- Application / Permit
- 21014-10000-00872
- Plan Check / Job No.
- B21LA03340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) FRONT PORCH. NEW ROOF FOR EXISTING REAR PORCH. CONVERT EXISTING ALCOVE TO A CLOSET.
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | HERNAN ARREOLA |
| Corrections Issued | 3/10/2021 | HERNAN ARREOLA |
| Plan Check Approved | 4/5/2021 | HERNAN ARREOLA |
| Issued | 6/4/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| CofO in Progress | 10/6/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| CofO Issued | 10/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | RENZ SORIANO |
Contact Information
| Contractor | Espana Builders; Lic. No.: 1002026-B | 6701 ETON AVE #104 WOODLAND HILLS, CA 91303 |
| Engineer | Billings,, Michael Tyrel; Lic. No.: S6408 | 3415 W 78TH ST LOS ANGELES, CA 90043 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/15/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/13/2021 | Corrections Issued | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/15/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/5/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/5/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/17/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/3/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/3/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 10/3/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/3/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 10/3/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/3/2022 | Approved | HAMIK HARTOUNIAN |