15122 W BURBANK BLVD 91411

Certificate Information: 15122 W BURBANK BLVD 91411

Application / Permit
21014-10000-00870
Plan Check / Job No.
B21LA03305
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 399 SF ADDITION ON FIRST FLOOR AND STORAGE. NEW ADU OVER (E) DETACHED GARAGE ON 2ND FLOOR PER ENGINEER DESIGN (1200 SF MAX PRE ORDINANCE, 12.22 A 33 (c) and (d))
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 7/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 AUNG SOE
Corrections Issued 3/30/2021 AUNG SOE
Quality Review Completed 4/5/2021 EUGENE BARBEAU
Applicant returned to address corrections 6/10/2021 AUNG SOE
Applicant returned to address corrections 9/7/2021 AUNG SOE
Plan Check Approved 9/8/2021 AUNG SOE
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 9/20/2021 APPLICANT
CofO in Progress 7/1/2022 ANDREW DORSO
Permit Finaled 7/5/2022 JEFFREY DURAN
CofO Issued 7/5/2022 JEFFREY DURAN
Permit Finaled 7/5/2022 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 4/22/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/22/2021 LEE GUILBEAUX
Highway dedication Cleared 4/22/2021 LEE GUILBEAUX
Sewer availability Cleared 4/22/2021 LEE GUILBEAUX
"Q" conditions Cleared 5/12/2021 ANACANY HURTADO
ZI Cleared 5/12/2021 ANACANY HURTADO
Hydrant and Access approval Cleared 6/4/2021 MATTHEW CRAIG
Low Impact Development Cleared 8/24/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/25/2021 DAGOVERTO GUERRERO
Tenant Habitability Plan Cleared 9/8/2021 ADRIENE ALLEN

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706
Engineer Moughraby,, Ousama; Lic. No.: C91595 9744 MAPLE ST      BELLFLOWER, CA 90706

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/21/2021 Partial Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 9/30/2021 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 10/1/2021 Approved ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Approved DANIEL VARNUM
Wood Frame 11/29/2021 Conditional Approval DANIEL VARNUM
Insulation 12/1/2021 Approved ANDREW DORSO
Interior/Exterior Lathing 12/1/2021 Corrections Issued ANDREW DORSO
Drywall Nailing 12/6/2021 Approved DANIEL VARNUM
Interior/Exterior Lathing 12/10/2021 Approved DANIEL VARNUM
BUILDING-Rough-Frame 3/3/2022 Approved DANIEL VARNUM
Final 3/3/2022 Partial Inspection DANIEL VARNUM
Green Building Final 3/3/2022 Approved DANIEL VARNUM
Green Building Rough 3/3/2022 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved DANIEL VARNUM
Smoke Detectors 3/3/2022 Approved DANIEL VARNUM
Final 7/1/2022 OK to Issue CofO ANDREW DORSO