3042 S CAVENDISH DR 90064

Certificate Information: 3042 S CAVENDISH DR 90064

Application / Permit
21014-10000-00869
Plan Check / Job No.
B21LA03300
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION OF AN (E) SINGLE STORY SINGLE FAMILY HOME WITH 965S OF NEW BEDROOM AND BATHROOMS ADDITION. 1. CONVERT (E) 400SF GARAGE INTO FAMILY ROOM 2. ADDITION OF 1 BEDROOM AND 2 BATHROOMS 3. ADDITION OF 2 CAR GARAGE NFPA 13-D FIRE SPRINKLERS THROUGHOUT. SEE COMMENTS
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 SERGIO GUTIERREZ
Corrections Issued 3/7/2021 SERGIO GUTIERREZ
Applicant returned to address corrections 6/30/2021 GEORGE ALVAREZ
Building Plans Picked Up 6/16/2022 APPLICANT
Plan Check Approved 6/22/2022 RAHEL BEYENE
Plan Check Approved 6/22/2022 GEORGE ALVAREZ
Issued 12/9/2022 APPLICANT
CofO in Progress 1/13/2025 JESUS RODRIGUEZ
CofO Issued 1/15/2025 RICHARD STEINBACH
Permit Finaled 1/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/17/2021 CATHERINE ADROVER
Permit Cleared 5/18/2021 CATHERINE ADROVER
Sewer availability Cleared 5/20/2021 CATHERINE ADROVER
Grading Pre-Inspection Cleared 6/30/2021 PATRICK MISCHLICH
GPI Written Notices Cleared 7/1/2021 SERGIO GUTIERREZ
Specific Plan Cleared 2/9/2022 EDUARDO HERMOSO
Low Impact Development Cleared 5/3/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 6/15/2022 CATHERINE ADROVER

Contact Information

Contractor 6050 Longridge Ave; Lic. No.: 878865-B       VALLEY GREEN, CA 91401
Engineer Chen,, Junfei; Lic. No.: C85841 726 FAMILY TREE      IRVINE, CA 92618

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/19/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/10/2023 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 3/17/2023 Corrections Issued ASHLEY THOMPSON
Piling/Pier/Caisson 3/17/2023 Not Ready for Inspection ASHLEY THOMPSON
Footing/Foundation/Slab 3/31/2023 Approved JEREMY TODD
Piling/Pier/Caisson 3/31/2023 Approved JEREMY TODD
Green Building Rough 4/27/2023 Not Ready for Inspection CLAYTON GRAHAM
Pre-Inspection 4/27/2023 Partial Inspection CLAYTON GRAHAM
Wood Frame 4/27/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 5/11/2023 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 5/11/2023 Partial Approval CLAYTON GRAHAM
Wood Frame 5/11/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 5/22/2023 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 5/22/2023 Partial Approval JOHNNY MIRANDA
Deputy Steel/Welding 6/23/2023 Conditional Approval DAVID FEILER
Deputy Drilled-In Anchors 8/18/2023 Conditional Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 9/12/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 9/12/2023 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Conditional Approval ARAM AVEDISIAN
Green Building Rough 9/12/2023 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 9/12/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/12/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 10/2/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Corrections Issued ARAM AVEDISIAN
Green Building Rough 10/2/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 10/2/2023 Approved ARAM AVEDISIAN
Shower Pan 10/2/2023 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 10/2/2023 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 10/6/2023 Partial Approval BEN MOLSTAD
Interior/Exterior Lathing 10/13/2023 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 11/29/2023 No Access for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/5/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/6/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 12/6/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 12/6/2023 Approved OGANES TARAKHCHYAN
Wood Frame 12/6/2023 Approved OGANES TARAKHCHYAN
Insulation 12/7/2023 Approved MICHAEL PELHAM
Drywall Nailing 12/12/2023 Approved OGANES TARAKHCHYAN
Gas Test 1/9/2024 Approved STEPHANIE SWANSON
Green Building Final 3/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 3/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 4/22/2024 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 4/22/2024 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 1/13/2025 Approved JESUS RODRIGUEZ
Final 1/13/2025 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 1/13/2025 Approved JESUS RODRIGUEZ
HVAC-Final 1/13/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/13/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 1/13/2025 Approved JESUS RODRIGUEZ