1707 W 247TH ST 90717
Certificate Information: 1707 W 247TH ST 90717
- Application / Permit
- 21014-10000-00844
- Plan Check / Job No.
- B21LA03242
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD TO EXTEND BEDROOM AND REMODEL AREA TO CREATE MASTER BATH AND WALK-IN CLOSET.
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 7/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | VU NGUYEN |
| Corrections Issued | 3/9/2021 | VU NGUYEN |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Plan Check Approved | 3/20/2021 | LUKE GONZALES |
| Issued | 3/23/2021 | APPLICANT |
| CofO in Progress | 7/12/2021 | ANSON MAGLASANG |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
| CofO Issued | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/11/2021 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 3/11/2021 | YEGANEH SADEGHI |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | YEGANEH SADEGHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim Chu Man; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 3/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 3/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/8/2021 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 4/10/2021 | Partial Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | EVAN COOPER |
| Insulation | 4/12/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/15/2021 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 4/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 4/15/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/28/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 4/28/2021 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 5/3/2021 | Approved | JOHN KLARIN |
| Insulation | 5/7/2021 | No Access for Inspection | SABAS ALONSO |
| Special/Order Compliance | 5/7/2021 | Approved | ANSON MAGLASANG |
| Insulation | 5/12/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 5/12/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 5/13/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Pre-Inspection | 5/13/2021 | Partial Inspection | ALAN MORELOS |
| Drywall Nailing | 5/14/2021 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 5/18/2021 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 5/18/2021 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | JOHN KLARIN |
| Final | 6/2/2021 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 6/2/2021 | Approved | JOHN KLARIN |
| Green Building Final | 6/2/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 6/2/2021 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Barrier | 6/2/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 6/2/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 6/2/2021 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 6/4/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 6/4/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/23/2021 | Conditional Approval | JOHN KLARIN |
| Final | 6/23/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 6/23/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 6/23/2021 | Approved | JOHN KLARIN |
| Final | 6/25/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | ANSON MAGLASANG |
| Final | 7/12/2021 | OK to Issue CofO | ANSON MAGLASANG |
| Green Building Final | 7/12/2021 | Approved | ANSON MAGLASANG |
| Green Building Rough | 7/12/2021 | Approved | ANSON MAGLASANG |