820 W SOLANO AVE 90012

Certificate Information: 820 W SOLANO AVE 90012

Application / Permit
21014-10000-00840
Plan Check / Job No.
B21LA03212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 KEVIN MORALES
Corrections Issued 3/10/2021 KEVIN MORALES
Applicant returned to address corrections 7/30/2021 KEVIN MORALES
Plan Check Approved 11/9/2021 FERNANDO FLORES
Issued 11/10/2021 APPLICANT
Building Plans Picked Up 11/15/2021 APPLICANT
CofO in Progress 5/30/2023 OSVALDO PARAMO
CofO in Progress 5/30/2023 OSVALDO PARAMO
CofO Issued 8/7/2023 DEROLD HAUFF
Permit Finaled 8/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/11/2021 JEANIE LAM
Grading Pre-Inspection Cleared 8/24/2021 PATRICK MISCHLICH
Low Impact Development Cleared 9/24/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/28/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2022 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 3/1/2022 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/1/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/9/2022 Corrections Issued OSVALDO PARAMO
Deputy Reinf. Concrete 3/10/2022 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 4/20/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/20/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/3/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 5/3/2022 Approved OSVALDO PARAMO
Green Building Rough 5/3/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 5/3/2022 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/17/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/1/2022 Approved OSVALDO PARAMO
Green Building Rough 7/1/2022 Approved OSVALDO PARAMO
Shower Pan 7/15/2022 Approved OSVALDO PARAMO
Insulation 8/3/2022 Approved OSVALDO PARAMO
Drywall Nailing 8/11/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/15/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready JULIAN AMAYA
Final 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Footing/Foundation/Slab 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Green Building Final 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Smoke Detectors 1/17/2023 Not Ready for Inspection JULIAN AMAYA
Final 1/30/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 1/30/2023 Approved OSVALDO PARAMO
Green Building Final 1/30/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 1/30/2023 Approved OSVALDO PARAMO
Final 5/23/2023 OK to Issue CofO OSVALDO PARAMO