1 E NORTHSTAR ST 1-15 90292

Certificate Information: 1 E NORTHSTAR ST 1-15 90292

Application / Permit
21014-10000-00767
Plan Check / Job No.
B21LA02960
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
ADD 55 SQ. FT, AND FIRE DAMAGE REPAIR LESS THAN 10% IN UNITS 205 & 305 OF A 3-STORY, TYPE VA, CONDOMINIUM WITH ATTACHED PARKING GARAGE.
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 KESETE HAREGOT
Corrections Issued 3/24/2021 KESETE HAREGOT
Quality Review Completed 3/25/2021 FARUK SEZER
Building Plans Picked Up 3/30/2021 APPLICANT
Green Plans Picked Up 5/3/2021 APPLICANT
Plan Check Approved 6/11/2021 KESETE HAREGOT
Plan Check Approved 6/11/2021 KESETE HAREGOT
Issued 6/30/2021 APPLICANT
CofO in Progress 1/30/2024 FARHAD DADBIN
Permit Finaled 2/12/2024 DAVID TSAU
CofO Issued 2/12/2024 DAVID TSAU
Permit Finaled 2/12/2024 DAVID TSAU

Permit Application Clearance Information

Specific Plan Cleared 4/6/2021 BINDU KANNAN
Green Code Cleared 5/3/2021 AARON COSTA

Contact Information

Contractor Ikon Builders Inc; Lic. No.: 966760-B 32158 CAMINO CAPISTRANO A 336      SAN JUAN CAPISTRANO, CA 92675
Engineer Hokama,, Michael Sigueo; Lic. No.: S4505 4 ST JUST AVE      LADERA RANCH, CA 92694

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 9/21/2021 Conditional Approval SORIN CIRSTOIU
Green Building Rough 10/7/2021 Approved NICK LAROCCA
METHANE-Rough 10/7/2021 Approved NICK LAROCCA
Wood Frame 10/7/2021 Partial Approval NICK LAROCCA
Wood Frame 10/25/2021 Partial Approval JOHN DODGE
Interior/Exterior Lathing 12/14/2021 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 11/1/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 5/24/2023 Approved FARHAD DADBIN
Final 11/17/2023 Corrections Issued AMANUEL BERHE
Footing/Foundation/Slab 11/17/2023 Approved AMANUEL BERHE
Green Building Final 11/17/2023 Approved AMANUEL BERHE
METHANE-Barrier 11/17/2023 Approved AMANUEL BERHE
METHANE-Subgrade 11/17/2023 Approved AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved AMANUEL BERHE
Smoke Detectors 11/17/2023 Approved AMANUEL BERHE
Wood Frame 11/17/2023 Approved AMANUEL BERHE
Final 1/26/2024 Conditional Approval FARHAD DADBIN
Final 1/30/2024 OK to Issue CofO FARHAD DADBIN
Special/Order Compliance 2/9/2024 Approved FARHAD DADBIN