1 E NORTHSTAR ST 1-15 90292
Certificate Information: 1 E NORTHSTAR ST 1-15 90292
- Application / Permit
- 21014-10000-00767
- Plan Check / Job No.
- B21LA02960
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- ADD 55 SQ. FT, AND FIRE DAMAGE REPAIR LESS THAN 10% IN UNITS 205 & 305 OF A 3-STORY, TYPE VA, CONDOMINIUM WITH ATTACHED PARKING GARAGE.
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | KESETE HAREGOT |
| Corrections Issued | 3/24/2021 | KESETE HAREGOT |
| Quality Review Completed | 3/25/2021 | FARUK SEZER |
| Building Plans Picked Up | 3/30/2021 | APPLICANT |
| Green Plans Picked Up | 5/3/2021 | APPLICANT |
| Plan Check Approved | 6/11/2021 | KESETE HAREGOT |
| Plan Check Approved | 6/11/2021 | KESETE HAREGOT |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 1/30/2024 | FARHAD DADBIN |
| Permit Finaled | 2/12/2024 | DAVID TSAU |
| CofO Issued | 2/12/2024 | DAVID TSAU |
| Permit Finaled | 2/12/2024 | DAVID TSAU |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/6/2021 | BINDU KANNAN |
| Green Code | Cleared | 5/3/2021 | AARON COSTA |
Contact Information
| Contractor | Ikon Builders Inc; Lic. No.: 966760-B | 32158 CAMINO CAPISTRANO A 336 SAN JUAN CAPISTRANO, CA 92675 |
| Engineer | Hokama,, Michael Sigueo; Lic. No.: S4505 | 4 ST JUST AVE LADERA RANCH, CA 92694 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 9/21/2021 | Conditional Approval | SORIN CIRSTOIU |
| Green Building Rough | 10/7/2021 | Approved | NICK LAROCCA |
| METHANE-Rough | 10/7/2021 | Approved | NICK LAROCCA |
| Wood Frame | 10/7/2021 | Partial Approval | NICK LAROCCA |
| Wood Frame | 10/25/2021 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 12/14/2021 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/24/2023 | Approved | FARHAD DADBIN |
| Final | 11/17/2023 | Corrections Issued | AMANUEL BERHE |
| Footing/Foundation/Slab | 11/17/2023 | Approved | AMANUEL BERHE |
| Green Building Final | 11/17/2023 | Approved | AMANUEL BERHE |
| METHANE-Barrier | 11/17/2023 | Approved | AMANUEL BERHE |
| METHANE-Subgrade | 11/17/2023 | Approved | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Approved | AMANUEL BERHE |
| Smoke Detectors | 11/17/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 11/17/2023 | Approved | AMANUEL BERHE |
| Final | 1/26/2024 | Conditional Approval | FARHAD DADBIN |
| Final | 1/30/2024 | OK to Issue CofO | FARHAD DADBIN |
| Special/Order Compliance | 2/9/2024 | Approved | FARHAD DADBIN |