3175 S ALMERIA ST 90731

Certificate Information: 3175 S ALMERIA ST 90731

Application / Permit
21014-10000-00727
Plan Check / Job No.
B21LA02801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD.NEW 464 SF GROUND FLOOR & NEW 2ND FLOOR ROOF DECK COVERED WITH NEW TRELLISES (409 S,F) TO (E) ONE STORY SINGLE FAMILY DWELLING & ADD ATTACHED UNCOVERED DECK OF 374 SF AT GROUND LEVEL & INTERIOR REMODEL OF (E) SFD
Permit Issued
Issued on 11/3/2022
Issuing Office
San Pedro
Current Status
Issued on 11/3/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/20/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 GARO TELMI
Corrections Issued 3/17/2021 GARO TELMI
Quality Review Completed 3/22/2021 KEN GILL
Building Plans Picked Up 3/30/2021 APPLICANT
Applicant returned to address corrections 6/17/2021 GARO TELMI
Applicant returned to address corrections 9/20/2022 GARO TELMI
Plan Check Approved 10/31/2022 GARO TELMI
Issued 11/3/2022 APPLICANT

Permit Application Clearance Information

Green Code Cleared 3/16/2021 GARO TELMI
Low Impact Development Cleared 3/2/2022 TA ANH
Roof/Waste drainage to street Cleared 3/21/2022 HUGO LOPEZ
Grading Pre-Inspection Cleared 3/24/2022 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 3/25/2022 HUGO LOPEZ
Coastal Zone Cleared 9/7/2022 SHASHA YU
GPI Written Notices Cleared 10/6/2022 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Adefeso,, Wole; Lic. No.: C63361 1620 CENTINELA AVE 304B      INGLEWOOD, CA 90302

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2022 Corrections Issued ANSON MAGLASANG
METHANE-Barrier 11/10/2022 Approved ANSON MAGLASANG
METHANE-Subgrade 11/10/2022 Approved ANSON MAGLASANG
Footing/Foundation/Slab 11/16/2022 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 12/20/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 12/22/2022 Partial Approval ANSON MAGLASANG
Green Building Rough 12/22/2022 Not Ready for Inspection ANSON MAGLASANG
METHANE-Rough 12/22/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 2/13/2023 Partial Approval ANSON MAGLASANG
Green Building Rough 2/13/2023 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 6/13/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 6/13/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved JOHN KLARIN
Gas Test 6/13/2023 Approved JOHN KLARIN
Green Building Rough 6/13/2023 Corrections Issued JOHN KLARIN
HVAC-Rough 6/13/2023 Approved JOHN KLARIN
PLUMBING-Rough 6/13/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/22/2023 Approved JOHN KLARIN
Gas Test 6/22/2023 Not Ready for Inspection JOHN KLARIN
Green Building Rough 6/22/2023 Approved JOHN KLARIN
Insulation 6/22/2023 Approved JOHN KLARIN
Drywall Nailing 6/28/2023 Approved JAMES CHAVEZ
Gas Test 8/8/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/8/2023 Partial Approval JAMES CHAVEZ
Shower Pan 9/21/2023 Approved ANSON MAGLASANG
Footing/Foundation/Slab 11/29/2023 Approved JAMES CHAVEZ
Green Building Final 11/29/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 11/29/2023 Approved JAMES CHAVEZ
Special/Order Compliance 11/29/2023 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/3/2024 Approved ANSON MAGLASANG
Final 4/26/2024 Corrections Issued ANSON MAGLASANG
Green Building Final 4/26/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved ANSON MAGLASANG