3811 1/2 S RIDGELEY DR 90008
Certificate Information: 3811 1/2 S RIDGELEY DR 90008
- Application / Permit
- 21014-10000-00726
- Plan Check / Job No.
- B21LA02800
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* REMODEL & ADDITION TO (E) SINGLE FAMILY DWELLING W/ATT GARAGE ADDING (N) 2ND STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e), WOOD DECK AT REAR
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Current Status
- Issued on 8/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | LAMAR DAVIS |
| Corrections Issued | 6/1/2021 | LAMAR DAVIS |
| Quality Review Completed | 6/6/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/21/2023 | DANIEL YIP |
| Issued | 8/10/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 12/4/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/4/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 7/18/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 8/3/2022 | LANNY MERRICK |
| Grading Pre-Inspection | Cleared | 8/3/2022 | LANNY MERRICK |
| Low Impact Development | Cleared | 12/15/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | AMAAN MALIK |
Contact Information
| Architect | Lo,, Yu-Ngok; Lic. No.: C31804 | 14315 SUMMERTIME LN CULVER CITY, CA 90230 |
| Contractor | Owner-Builder | , |
| Engineer | Richards,, Mark Lee; Lic. No.: C55146 | 3820 DEL AMO BLVD STE 344 TORRANCE, CA 90503 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/14/2024 | Conditional Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/30/2024 | Partial Approval | ANTHONY EGSON |
| Deputy Reinf. Concrete | 10/3/2024 | Conditional Approval | ANTHONY EGSON |
| Wood Frame | 10/18/2024 | Partial Approval | ANTHONY EGSON |
| Insulation | 10/22/2024 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 11/13/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 2/10/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 2/20/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 3/21/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 3/21/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 3/21/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/1/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 5/1/2025 | Approved | LUIS CASTRO |
| Insulation | 5/1/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 6/6/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 7/15/2025 | Approved | LUIS CASTRO |
| Shower Pan | 9/15/2025 | Approved | RONNIE MEDINA |
| Pre-Inspection | 11/4/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 1/26/2026 | Approved | LUIS CASTRO |