6185 E ROY ST 90042
Certificate Information: 6185 E ROY ST 90042
- Application / Permit
- 21014-10000-00722
- Plan Check / Job No.
- B21LA02784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** 13' x 11.5' ADDITION TO EXISTING 1 STORY ADU
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 2/23/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/1/2021 | MINYE PAK |
| Plan Check Approved | 4/21/2021 | CRYSTEL MAALOUF |
| Issued | 5/4/2021 | APPLICANT |
| CofO in Progress | 12/8/2021 | COREY HUPP |
| CofO in Progress | 12/8/2021 | COREY HUPP |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/3/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | ROSA SILVA |
| GPI Written Notices | Cleared | 4/21/2021 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 4/21/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 5/12/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 5/25/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 5/25/2021 | Approved | COREY HUPP |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | COREY HUPP |
| Insulation | 6/3/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/3/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/9/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/25/2021 | Approved | COREY HUPP |
| Final | 6/25/2021 | OK to Issue CofO | COREY HUPP |
| Green Building Final | 6/25/2021 | Approved | COREY HUPP |
| Green Building Rough | 6/25/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 6/25/2021 | Approved | COREY HUPP |